Operational control of construction and installation works. Cards of operational quality control of the main construction and installation works

11.9.1 During the performance of production processes and operations, operational control is carried out in order to identify defects that may be hidden during the continuation of the process or operation, and to take measures to prevent and eliminate these defects.

11.9.2 By operational control, the person carrying out the construction checks:

Compliance with the sequence and composition of the technological operations performed by the technological and regulatory documentation applicable to these technological operations;

Compliance with the technological regimes established technological maps and regulations;

Compliance of the quality indicators of the performance of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations.

11.9.2 During the construction process, an assessment of the work performed, the results of which affect safety, should be carried out. object, but in accordance with the accepted technology, they become unavailable for control after the start of the subsequent work, as well as the completed building structures and sections of engineering networks, the elimination of defects of which, identified by the control, is impossible without dismantling or damaging subsequent structures and sections of engineering networks. Representatives of the relevant bodies of state supervision, architectural supervision, as well as, if necessary, independent experts may participate in these control procedures. The performer of works not later than three working days notifies the other participants about the timing of the specified procedures.

11.9.3 The results of the acceptance of work hidden by subsequent work, in accordance with the requirements of the design and regulatory documentation, are documented in certificates of survey of hidden work ( Annex M ). The builder (customer) may require a re-examination after the elimination of the identified defects.

11.9.4 To the procedure for assessing the conformity of individual structures, tiers of structures (floors), the performer of the work must submit certificates of survey of all hidden works that are part of these structures, geodetic executive schemes, as well as test reports for structures in cases provided for by the design documentation and (or) building contract. The developer (customer) can perform verification of the reliability of the executive geodetic schemes submitted by the contractor. To this end, the performer of the work must keep, until the completion of the acceptance, the alignment axes and mounting landmarks fixed in kind.

The results of acceptance of individual structures should be documented in acts of acceptance of critical structures ( annex H ).

11.9.5 Tests of sections of engineering networks and installed engineering equipment are carried out in accordance with the requirements of the relevant regulatory documents and are documented in acts of acceptance of critical structures (Appendix H).

11.9.6 If, as a result of phased acceptance, defects in works, structures, sections of engineering networks are detected, the relevant acts should be drawn up only after the identified defects have been eliminated.

In cases where subsequent work must begin after a break of more than 6 months from the moment the phased acceptance is completed, these procedures should be repeated before the resumption of work with the execution of the relevant acts.

11.9.7 Places for performing control operations, their frequency, performers, methods and measuring instruments, forms for recording results, decision-making procedures in case of detection of non-compliance with established requirements must comply with the requirements of design, technological and regulatory documentation.

11.9.8 The person carrying out the construction appoints by its administrative documents responsible executors for the performance of operational control, documentation of its results and elimination of defects identified by the control.

The results of operational control should be documented in special work logs.

Design and Technological Institute of Industrial Construction

OJSC PKTIpromstroy

CHARTS OF OPERATIONAL QUALITY CONTROL OF MAIN CONSTRUCTION AND ASSEMBLY WORKS

1. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF REINFORCED CONCRETE COLUMNS

2. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF LARGE-BLOCK TAPE FOUNDATIONS

3. OPERATIONAL CONTROL CHART DURING INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

4. OPERATIONAL CONTROL CHART DURING INSTALLATION OF CAMs

5. OPERATIONAL CONTROL CHART OF THE INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS

6. CHART OF OPERATIONAL CONTROL OF THE INSTALLATION OF FLOOR PANELS (COATINGS)

7. OPERATIONAL CONTROL CHART FOR WALL FORMWORK INSTALLATION

8. OPERATIONAL CONTROL CHART INSTALLATION OF FORMWORK COLUMNS AND FLOORS

9. OPERATIONAL CONTROL CHART WHEN INSTALLING THE FOUNDATION FORMWORK

10. KAPTA OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT

11. CHART OF OPERATIONAL CONTROL OF CONCRETING SLABS

12. WALL CONCRETING OPERATIONAL CONTROL CHART

13. COLUMN CONCRETING OPERATIONAL CONTROL CHART

14. OPERATIONAL CONTROL CARD FOR BRICK PILLARS

15. OPERATIONAL CONTROL CARD FOR BRICK WALLS

16. OPERATIONAL CONTROL CHART INSTALLATION OF WINDOW AND DOOR UNITS

The technological map does not replace the commissioning (see SNiP 3.01.01-85 *) The quality of construction and installation works is characterized by the degree of their compliance with the requirements of projects and SNiP. Any deviation from these requirements must be detected and corrected in a timely manner, which can only be achieved through the organization of daily operational quality control. Operational quality control of construction installation work is carried out by the manufacturer of works and the foreman, with the involvement, if necessary, of representatives of the quality control laboratory of the trust (association). The main tasks of operational quality control of construction and installation works: - ensuring the required level of quality of the buildings under construction; - ensuring the implementation of construction and installation works in accordance with the project and the requirements of regulatory documents; - timely identification of the causes of defects in the production of works and the adoption of measures to eliminate them; - increasing the personal responsibility of direct executors and line engineering and technical workers for the quality of construction and installation works performed. All defects identified during the operational control must be eliminated before the start of subsequent operations (works). Operational control must be carried out in strict accordance with the enterprise standard (STP) "Regulations on operational quality control". The main documents of operational quality control are operational control cards. They must be constantly at the facilities under construction with the construction manager and presented at the request of persons controlling the quality of work. They indicate the duties of officials in the implementation of operational control. If the work at the facility is headed by one manager (foreman, foreman), then he performs all the control functions indicated in the operational control cards. Operational quality control cards are intended for line engineering and technical workers and foremen, and can also be used by persons exercising quality control over construction.

1. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF REINFORCED CONCRETE COLUMNS

Tolerances for the installation of reinforced concrete columns in accordance with the requirements of SNiP 1. Difference in elevations of the tops of adjacent columns or support platforms (brackets, consoles) ± 10mm 2. Difference in elevations of the tops of columns or support platforms within the area to be verified: with a contact installation 12 + 2, where - serial number of the tier when installed on beacons 10 mm 3. Offset of the axes of the columns of one-story buildings in the upper section from the vertical at the height of the columns H: in meters up to 10 m ± 10 mm over 10 m 0.001 N, but not more than 35 mm 4. Offset of the axes of the columns multi-storey buildings in the upper section relative to the center lines for columns with a height of up to 4.5 m ± 10 mm over 4.6 m ± 15 mm

Table 1

Operations subject to control

Composition of control

Control method

Control time

Works

Activated works

Work Producer

Preparatory work

Proper warehousing

Visually

Before installation

Elevation of the bottom of the foundation glass

With the help of a level

Before installation

Surveyor

Installation of columns

Reliability of slinging, verticality of installation, alignment; marks of reference platforms; temporary fastening

Visually; with the help of a level; using a theodolite

During installation

Surveyor

Welding of metal parts

Weld quality

Visually

During installation

Anti-corrosion protection of metal parts

Visually

During installation

If necessary, the laboratory

Casting columns

Carefulness of monolithic

Visually

During installation

Preparatory work(reception of designs)

Availability of passports, drawings, geometric dimensions, external defects, drawing of center axes, marks, dimensions of support areas, correct location of embedded parts

Visually; with a steel meter

Before installation

Preparation of column installation sites

Cleaning glasses, dimensions of the foundation glass; the presence of risks on the foundation

Before installation

Mounting hardware installation

Fixture fixing accuracy

Visually

During installation

Welding of metal parts

Compliance with the project; welding of electrodes; seam dimensions

Visually

During installation

Laboratory

Embedding columns in foundations

Grade, consistency of concrete mix, thoroughness of compaction

Visually, using a standard cone

During installation

Laboratory

2. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF LARGE-BLOCK TAPE FOUNDATIONS

Tolerances for the installation of large-block strip foundations in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of foundation blocks and blocks of foundation walls relative to the center axes ± 10 mm 2. Deviation of the marks of the upper supporting surfaces of the foundation elements - 10 mm 3. Displacement of axes or faces wall blocks in lower section relative to the center axes or geometric axes below installed structures± 5mm

table 2

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Determining the state of soils

Visually

Before installation

The correct location of the pit relative to the layout drawing, the reliability of fastening, the elevation of the bottom of the pit

Visually, using a level and tape measure

Before installation

Surveyor

Marking the top of a sand or gravel pad

With the help of a level

Before installation

Surveyor

Proper warehousing

Visually

Before installation

Breakdown of axes of foundations

The accuracy of determining the position of the corners of the building. Compliance with the project of distances between the axes of prefabricated foundations

With theodolite and tape measure

Before installation

Surveyor

Installation of foundation blocks

Visually

During installation

Accuracy of installation, foundation blocks. Density of support and abutment

With level and plumb

During installation

Compliance of marks with design

With the help of a level

After installing the blocks

Surveyor

Preparatory work

Sufficiency of the sizes of pits

With the help of a tape measure

Before installation

The thickness of the sand or gravel cushion, the quality of its compaction

Visually, using a steel meter

Before installation

Cleaning foundation blocks from dirt, from snow in winter

Visually

Before installation

Availability of passports for reinforced concrete structures; correspondence of the geometric dimensions of the blocks to the project; external defects

Roulette

Before installation

Breakdown of foundation axes

The correctness of the tension of the axes, the accuracy of the intersection of the axes on the foundation blocks

With a theodolite

Before installation

Surveyor

Installation of foundation blocks

Compliance with installation technology, Technological map

Visually

During installation

3. OPERATIONAL CONTROL CHART DURING INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

Tolerances during the installation of reinforced concrete foundations for columns in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of the foundation cups relative to the center axes ± 10mm 2. Deviation of the marks of the upper supporting surfaces of the foundation elements - 10mm 3. Deviation of the bottom marks of the foundation cups - 20mm

Table 3

Operations subject to control

Composition of control

Control method

Control time

Activated works

Work Producer

Preparatory work

Preparation of the base for foundations, its condition, dimensions, marks, protection against freezing in winter

With the help of a level, steel meter, tape measure

Before installation

Surveyor

The dimensions of the pits, the correctness of their location and the reliability of fastening the walls of the pit, the marks of the bottom of the pit

Visually, using a level, tape measure, plumb line

Before installation

Base top elevation and cushion levelness

With the help of a level

Before installation

Surveyor

Lateral waterproofing of foundation blocks

Insulation quality

Visually

After installation

Preparatory work

The thickness of the sand or gravel pad and the quality of its compaction

Visually i with a steel meter

Before installation

Cleaning from dirt, in winter from snow and ice

Visually

Before installation

Checking the geometric dimensions of blocks, defects. Comparison of passport data of reinforced concrete structures with design

Before installation

Installation of control sights along the axes of the foundations

Compliance with the design of the axles transferred to the bottom of the pit.

The accuracy of the position of the top of the control sights

With the help of a theodolite, a level

Before installation

Installation and alignment of blocks

Installation accuracy, compliance with design marks and axes

With the help of a level

During installation

Surveyor

4. OPERATIONAL CONTROL CHART DURING INSTALLATION OF CAMs

Tolerances for the installation of crossbars in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of the crossbars along the lower belt relative to the geometric axes of the supporting structures ± 6 mm 2. Deviation of the distances between the axes of the crossbars at the level of the upper chords ± 20mm 3. The tolerances of the support areas and the tolerances of the gaps between the elements are determined by the project

Table 4

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Proper storage of structures

Visually

Before installation

Alignment of bearing surfaces on columns

Correspondence of the marks of the supporting platforms of the columns with the design ones, the correctness of the marking axes

With the help of a theodolite, level, steel meter

Before installation

Surveyor

Installation of crossbars

Correctness and reliability of slinging

Visually

During installation

Alignment of the axes of the crossbar with the center axes on the supporting structures, the verticality and density of the support of the crossbar

Visually, with a plumb line

During installation

Welding of embedded parts in joints

Visually, using a steel meter

During installation

If necessary, the laboratory

Sealing joints

External type of joints, strength of concrete at the joint

Visually, using a reference hammer

After stripping the joint

Laboratory

Preparatory work

Compliance of the geometric dimensions with the design ones, external defects, the presence of passports, the correct location of embedded parts, their cleaning

Visually, using a steel meter, tape measure

Before installation

Alignment of bearing surfaces on columns

Visually, using a steel meter

Installation of crossbars

Correctness of drawing axial and control marks on crossbars

Visually, using a steel meter, tape measure

During installation

Visually

During installation

Compliance with the design of the joint and the brand of electrodes according to the project

Visually

During installation

Sealing joints

The density and strength of the formwork

Visually

During installation

Concrete brand

Before concreting

Laboratory

Joint seal quality

Visually

During the concreting process

Joint filling quality

Visually

After stripping

5. OPERATIONAL CONTROL CHART OF THE INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS

Tolerances for the installation of reinforced concrete trusses and beams in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of trusses (beams) along the lower chord relative to the geometric axes of the supporting structures ± 5mm 2. Deviation of the distances between the axes of trusses (beams) at the level of the upper chords ± 20 mm 3. Tolerances of support areas and tolerances of gaps between elements are determined by the project

Table 5

Quality Control Persons

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Proper storage of reinforced concrete structures

Visually

Before installation

Alignment of supporting surfaces of previously assembled structures

Compliance of the marks of the reference platforms with the design ones, the correctness of the marking axes

Before installation

Surveyor

Installation of trusses, beams

Correctness and reliability of slinging

Visually

During installation

Alignment of beam truss axes with center axes, verticality of support structures

Visually, with a plumb line

During installation

Reliability of temporary fastening

Visually

During installation

Welding of embedded parts in joints

Quality of welding, certificates of acceptance of welded joints, dimensions of welds

Visually, using a steel meter

In the process of installation

Anti-corrosion protection

The quality of the application of the anti-corrosion layer

Visually

Before monolithic

If necessary, the laboratory

Preparatory work

Availability of passports, geometric dimensions, external defects, reinforced concrete structures

Visually, using a steel meter

Before installation

The location of embedded parts, cleaning them from rust and concrete sagging

Visually, using a steel meter

Before installation

Alignment of supporting surfaces of structures

The position of the support pads and embedded parts

Visually

Before installation

Installation of beam trusses

Presence and correctness of drawing axial and control marks on structures

With a steel meter

During installation

Correct installation technology

Visually

During installation

Welding of embedded parts in joints

Type of electrodes, joint compliance with the project

Visually

During installation

Sealing joints

The density and strength of the formwork

Visually

Before concreting

Concrete grade, compaction quality

Visually

In the process of monolithic

Laboratory

The appearance of the joint, the quality of the seal

Visually

In the process of monolithic

Compliance of the marks of the installed structures with the design ones, the distance between the axes

Visually

After installation

Surveyor

6. CHART OF OPERATIONAL CONTROL OF THE INSTALLATION OF FLOOR PANELS (COATINGS)

Tolerances for the installation of floor panels (coverings) in accordance with the requirements of SNiP III -16-73 1. The difference in elevations of the front surfaces of two adjacent floor slabs (coverings) at the joint ± 5 mm supporting surfaces and truss nodes and other load-bearing structures(along the supporting sides of the slabs), not allowed 3. Permissible deviations in the dimensions of the support areas and gaps between structural elements are determined by the project

Table 6

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved with control

Activated works

Work Producer

Preparatory work

Proper stacking of panels

Visually

Before installation

Compliance of marks and support sites with design

With the help of a level, tape measure, steel meter

Before installation

Surveyor

Installation of floor panels

Instrumental check of the installation horizon of each floor

With the help of a level

During installation

Surveyor

Anti-corrosion protection of anchors

The quality of the anti-corrosion coating

Visually

Fastening joints

Laboratory

Sealing joints

The quality of the monolithic joints

Visually

After monolithic

Preparatory work

Availability of passports, geometrical changes, surface quality of structures

Before installation

Correct location of embedded parts, mounting loops

Visually, using a tape measure, a steel meter

Before installation

Execution of the supporting row of brickwork by poking

Visually

Before installation

Mortar bed making

Correspondence of the grade of mortar to the project, the thickness of the mortar layer

Visually

During installation

Laboratory

Panel mounting

Compliance with the area of ​​support, the position of the panel in plan, the density of contact with the supporting surface, the correct installation technology

Visually

During installation

Panel anchoring

Compliance of anchoring with project requirements

Visually

Before monolithic

Sealing joints

Cleaning and moistening of the surfaces to be joined, compliance of the brand of mortar or concrete with the design ones

In the process of monolithic

Laboratory

7. OPERATIONAL CONTROL CHART FOR WALL FORMWORK INSTALLATION

Tolerances when installing wall formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design slope of the wall formwork planes and their intersection lines with wall heights up to 5 m 10 mm with wall heights over 5 m 15 mm 2. Offset of wall formwork axes : from the design position 8 mm 3. Internal dimensions of the wall formwork from the design dimensions 3 mm 4. Local irregularities of the formwork when checking with a two-meter rail 3 mm

Table 7

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Visually

Before formwork installation

Formwork installation

After installing the wall formwork (before it is fixed)

Surveyor

Accuracy of installation of embedded parts, their fastening

With the help of a meter, tape measure

After installing the formwork

Preparatory work

Compliance with the project and the quality of formwork panels, correct storage

Visually, with a meter

Before formwork installation

Formwork installation

Compliance with design dimensions, verticality

With the help of a meter, a plumb line

During formwork installation

Formwork fixing quality

Visually

During formwork installation

The quality of the inner surface of the formwork

During formwork installation

8. OPERATIONAL CONTROL CHART INSTALLATION OF FORMWORK COLUMNS AND FLOORS

Tolerances for the installation of the formwork of columns and ceilings in accordance with the requirements of SNiP III -15-76 1. The distance between the supports of the bent formwork elements and the distance between the ties of the vertical supporting structures from the design dimensions: per 1 m of length 25 mm for the entire span at least 75 mm 2. Distance from the vertical or the design slope of the formwork planes and their intersection lines: by 1 m of height 5 mm for the entire height of columns up to 5 m 10 mm - "- more than 5 m 15 mm for the entire height of the beams 5 mm 3. Displacement of the formwork axes from the design position of the columns 8 mm - "- beams 10 mm 4. The distance between the inner surfaces of the formwork of columns, beams from the design dimensions - 3 mm 5. Local irregularities of the formwork when checking with a 2-meter rail - 3 mm

Table 8

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Determination of the state of the base (for columns)

Visually

Before formwork installation

Formwork installation

Compliance of supporting scaffolding and scaffolding with the project, their stability and rigidity

Visually, using a steel meter, tape measure, plumb line

Before formwork installation

Correspondence of the formwork position to the installation axes

Using a theodolite, plumb line, tape measure

During formwork installation

Surveyor

Installation accuracy of embedded parts

With a steel meter, tape measure

Formwork Ambassador

Preparatory work

The quality of formwork panels and fasteners

Visually, using a steel meter

Before formwork installation

Proper storage of formwork elements

Visually

Before formwork installation

Formwork installation

Compliance with design dimensions and marks

With the help of a level, plumb line, level, steel meter, tape measure

During formwork installation

Formwork surface quality (density at the interface of boards)

Visually, using a 2-meter rail

During formwork installation

Formwork fastening quality

Visually

During formwork installation

9. OPERATIONAL CONTROL CHART WHEN INSTALLING THE FOUNDATION FORMWORK

Tolerances when installing the foundation formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design position of the foundation formwork planes and lines of their intersections per 1 m height 5mm 2. Offset of foundation formwork axes from the design position of 15mm foundations for steel structures , (L - length of the span or step of the structure, m) 3. Local irregularities of the formwork (when checking with a rail 2 m long) 3 mm

Table 9

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Determination of the state of the base

Visually

Before formwork installation

Formwork installation

Compliance with the position of the formwork to the installation axes, the accuracy of the installation of embedded parts and their fastening

With the help of a theodolite, tape measure, plumb line, steel meter

After installing the formwork

Surveyor

Preparatory work

Compliance with the design and quality of formwork panels, blocks and fasteners, correct storage of formwork elements

Visually, using a steel meter

Before formwork installation

Formwork installation

Compliance with design dimensions and marks. Horizontal and vertical formwork elements, quality of fasteners, quality of the inner surface of the formwork

Visually, using a level, plumb line, steel meter

During formwork installation

10. KAPTA OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT

Tolerances for reinforcement of structures in accordance with the requirements of SNiP III -15-76 1. Reinforcing steel supplied for construction must be subjected to external inspection upon acceptance. measurements and control tests in cases stipulated in the project 2. The replacement of the reinforcing steel provided for by the project is agreed with the design organization 3. Before mounting the reinforcement, the formwork is checked, the linings are fixed, providing a gap for the protective layer equipment 4. The mounted reinforcement is fixed from displacement and protected from damage during concreting 5. The displacement of reinforcing bars when they are installed in the formwork should not exceed 1/5 of the largest diameter of the bar and 1/4 of the diameter of the installed bar
Table 10

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Reinforcement acceptance

Compliance of reinforcing meshes and frames with the project (passport)

Visually

Before installation

Reinforcement installation

Installation of grids, frames, embedded parts in accordance with the project

With the help of a plumb line, a steel meter

During installation

Providing a protective layer

With a steel meter

When installing formwork

Fixing joints, frames, meshes (welding, knitting)

Visually

After fixing

Laboratory

Reinforcement acceptance

It is carried out selectively The diameter of the reinforcement, the distance between the working rods in meshes and frames are checked

With a caliper and a steel meter

Before installation

Embedded parts position

With a steel meter

Before installation

The quality of the reinforcement fastening points in the mesh frame

Visually

Before installation

Armature storage

Proper warehousing and storage

Visually

Before installation

Correct slinging

Visually, using a steel meter

During installation of fittings

Reinforcement installation

Compliance with the technology adopted in the technological map or commissioning

Visually

During installation of fittings

The correct layout of the grids, the correct fixing of the reinforcement in the formwork

Visually, using a steel meter

During installation of fittings

Correct installation of running boards on the slab

Visually

During installation of fittings

11. CHART OF OPERATIONAL CONTROL OF CONCRETING SLABS

Tolerances for concreting floors in accordance with the requirements of SNiP III -15-76 1. Local deviations of the concrete surface from the design when checking structures with a rail 2 m long ± 5 mm 2. In the marks of surfaces and embedded parts that serve as supports for metal or precast concrete elements ± 5 mm 3. In the location of anchor bolts, in plan inside the contour of the support - 5 mm in plan outside the contour of the support - 10 mm 4. Difference of marks in height at the junction of two adjacent surfaces - 3 mm

Table 11

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Condition of reinforcement and embedded parts, act of acceptance of reinforcement

Visually

Before concreting

Stripping

Surface quality, compliance with the design of holes, geometric dimensions

Visually, with a meter

After stripping

The strength of concrete, its uniformity, the presence of cracks

Visual, ultrasonic device

After stripping

Laboratory

Preparatory work

Base quality, removal of the top layer during working seams, notching, washing

Visually

Before concreting

Concrete laying

The quality of the concrete mix

With the help of the StroyTsNIIL cone, the press

Before concreting

Laboratory

Visually

During installation

Visually

During installation

Outside temperature

With a thermometer

During installation

Concrete compaction

Transposition step and immersion depth of vibrators

Visually

During compaction

Sufficiency of vibration and thickness of the concrete layer during compaction

Visually

During compaction

Curing concrete care

With a thermometer

During the curing process

12. WALL CONCRETING OPERATIONAL CONTROL CHART

Tolerances for concreting walls in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or design slope to the full height: walls supporting monolithic coatings and floors ± 15mm walls supporting precast beam structures ± 10mm 2. Horizontal planes on the entire plane of the verified area ± 20mm 3. Local deviations of the concrete surface from the design when checking the structure with a rail 2 m long ± 5 mm 4. In the marks of surfaces and embedded parts - 5 mm

Table 12

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Compliance with the design elevation of the base

With the help of a level

Before concreting

Surveyor

Condition of fittings and embedded parts, act of acceptance of fittings

Visually

Before concreting

Stripping

Surface quality, compliance with the design of holes, openings, channels, geometric dimensions

Visually, using a steel meter

After stripping

The strength of concrete, its uniformity, the presence of supports, cracks

With the help of an ultrasonic device, visually

After stripping

Laboratory

Preparatory work

The quality of the base, the removal of the top layer at the working seams, notch, prominka, the presence of waterproofing

Visually

Before concreting

Concrete laying

The quality of the concrete mixture (mobility, cubic strength)

Before concreting

Laboratory

The correctness of the technology of laying the concrete mix

Visually

During installation

Correct execution of work seams

Visually

During installation

Temperature of outdoor air and concrete mixture (in winter)

With a thermometer

During installation

Concrete compaction

Transposition step and immersion depth of vibrators

Visually, using a steel meter

During compaction

Sufficiency of vibration and thickness of the concrete layer during laying

Visually, using a steel meter

During compaction

Compliance with humidity and temperature conditions

With a thermometer

During the curing process

13. COLUMN CONCRETING OPERATIONAL CONTROL CHART

Tolerances during concreting in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or from the design slope to the entire height of columns supporting monolithic coatings and floors ± 15 mm Same, for columns supporting precast beam structures ± 10 mm 2. Horizontal planes on the entire plane of the area to be verified ± 20 mm 3. Local deviations of the concrete surface from the design when checking structures with a rail 2 m long, except for supporting surfaces ± 6 mm 4. In the dimensions of the cross-section of elements + 6 mm - 3 mm 5. In the marks of surfaces and embedded parts that serve as supports for metal or precast concrete elements - 5 mm

Table 13

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons or units involved in control

Activated works

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Compliance with the design elevation of the base

With the help of a level

Before concreting

Surveyor

Condition of reinforcement, embedded parts, act of acceptance of reinforcement

Visually

Before concreting

Stripping

Determination of surface quality, compliance with the project of geometric dimensions, correct location of embedded parts, marks of the top of columns

Visually, using a steel meter, level

After stripping

Surveyor

Determination of the strength of concrete, its uniformity

Using ultrasonic devices

After stripping

Laboratory

Preparatory work

Determining the quality of the base (cleaning from dirt, ice, snow, etc.)

Visually

Before concreting

Concrete laying

Determination of the quality of the concrete mixture (mobility, cubic strength)

With the help of the StroyTsNIIL cone, press (PSU-500)

Before laying in the structure

Laboratory

Compliance with concrete laying technology

Visually

During installation

Concrete compaction

Temperature control of outdoor air and concrete mix (in winter)

With a thermometer

During installation

Compliance with the permutation step and the depth of immersion of the vibrators, the correctness of their installation

Visually, using a steel meter

During compaction

Determination of vibration sufficiency and concrete layer thickness

Visually, using a steel meter

During compaction

Concrete care during hardening

Compliance with humidity and temperature conditions

With a thermometer

During the curing process

Laboratory

14. OPERATIONAL CONTROL CARD FOR BRICK PILLARS

Tolerances for masonry pillars in accordance with the requirements of SNiP III -17-78 1. Deviations from the design dimensions: 10mm in thickness, 10mm in marks of cutoffs and floors, 10mm in displacement of the axes of structures 10mm 2. Deviation of masonry surfaces and angles from the vertical: one floor 10mm 30mm for the whole building

Table 14

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

The correctness of the binding of poles to the center axes

Visually, with a plumb line

Before the start of laying

Brickwork pillars

Determination of the correct masonry technology and ligation of seams

With the help of a plumb line, a steel meter, visually

In the process of laying

Determining the conformity of the actual position of the performed brick pillars project, alignment of pillars of different floors

Visually, using a plumb line, steel meter

In the process of laying

Marking the edges of brickwork and floors, the correct arrangement of the pillow under the beams, the support of the beams on the pillows and their embedding in the masonry

Visually, using a level, a steel meter

After installing the pillow and installing the beam

Surveyor

Preparatory work

Determination of the base for the pillars, the presence of waterproofing

Visually

Before pole laying

Determination of the quality of bricks, reinforcement, embedded parts

Visually, measuring, checking passports and certificates

Before pole laying

Laboratory

Brickwork pillars

Dimensions, filling and dressing of seams;

With a steel meter

After every 5 m of laying

Geometric dimensions of the section of the pillars

With a steel meter

During the masonry process

Verticality of masonry, unevenness on the surface

With the help of a plumb line, rail, steel meter

After the completion of the laying of the pillar to the height of the floor

Masonry reinforcement

The correct location of the reinforcement, the distance between the grids along the height of the column, the diameter of the rods and the distance between them

With a steel meter, caliper

As the reinforcement is laid

15. OPERATIONAL CONTROL CARD FOR BRICK WALLS

Tolerances for masonry walls in accordance with the requirements of SNiP III -17-78 1. Deviation from design dimensions; by thickness 15 mm by marks of edges and floors 10 mm by width of piers 15 mm by width of openings 15 mm by displacement of axes of adjacent window openings 20 mm by the displacement of the axes of the structures 10 mm 2. Deviations of the surfaces and corners of the masonry from the vertical: one floor 10 mm for the entire building 30 mm 3. Deviations of the rows of masonry from the horizontal by 10 m in length 15 mm 4. Irregularities on the vertical surface of the masonry, detected when overlaying a 2-meter rail 10 mm

Table 15

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Brickwork walls.

The quality of bricks, mortar, fittings, embedded parts

External inspection, measurement, verification of passports and certificates

Before the laying of the walls of the floor

In case of doubt - laboratory

The correctness of the breakdown of the axes

With a steel tape measure, meter

Before the start of laying

Horizontal marks of masonry cutouts

Using a level, staff.level

Before installing floor panels

Surveyor

Alignment of ventilation ducts and sealing of ventilation units

Visually, with a plumb line

After finishing the laying of the walls of the floor

Masonry reinforcement

The correct location of the reinforcement, the diameter of the rods, etc.

Visually, using a steel meter

Before fittings

Prefabricated installation reinforced concrete slabs floors

Supporting floors on groans, embedding, anchoring

Visually, using a steel meter

After installing the cover

Anti-corrosion coating of embedded parts

Thickness, density and adhesion of the coating

Visually, using a thickness gauge, engraving shchitel

Before termination

Laboratory

Installation of balconies

Seal, mark, slope of balconies

Using a steel meter, level, 2-meter rail

After installing balconies

Brickwork walls

Geometric masonry dimensions

With a steel tape measure, meter

Verticality, horizontality and masonry surface

Using a level, rail, plumb

During and after the laying of the walls of the floor

Quality of masonry seams

With steel meter, 2 meter rail

After completing every 10m 3 masonry

Breakdown and marks of the bottom of the openings

With the help of a steel tape measure. level, level

Before the start of laying the walls

Removal of the mark + 1m from the finished floor

With the help of a level

After finishing the laying of the floor

Apartment layout

Visually

After the start of laying the walls

Geometric dimensions of the premises

With steel tape measure

After the start of laying the walls

Jumper setting

Jumper position, support, placement, termination

Visually, using a steel meter

After installing jumpers

Installation landings

Position of pistil areas, support, placement, incorporation

Visually, using a steel meter

After installing the platforms

Welding of embedded parts

Length, height, quality of welds

Visually, by tapping with a hammer

Before anti-corrosion coating

Soundproofing device

Construction, workmanship

Visually

Immediately after finishing work

16. OPERATIONAL CONTROL CHART INSTALLATION OF WINDOW AND DOOR UNITS

Rules for installing window and door blocks in accordance with the requirements of SNiP III -19-76 1. Surfaces of window and door blocks adjacent to stone walls, antiseptic with waterproofing materials 2. Gaps between the frame and masonry of the outer walls are sealed with thermal insulation materials 3. Window and door frames in stone walls and partitions are fastened with screws or steel ruffs driven into wooden antiseptic corks. Each vertical bar of the box is fixed in at least 2 places, the distance between them does not exceed 1 meter
Table 16

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Work Producer

Preparatory work

Appearance, factory readiness, compliance with standards, ENiP and the project, completeness of delivery of window and door units, availability of antiseptic acts

Visually

When accepting blocks

The presence of antiseptic plugs for fastening blocks

Visually

Before block installation

Conditions of transportation and storage

Visually

At the construction site

Installation of door and window units

Correct installation at a given elevation and along a given axis

Using a level, plumb line, tape measure

After installing the boxes

Box fixing

Visually

After installing the boxes

Density of fit of window and door frames

Visually

After installing the boxes

Waterproofing of the junction of blocks to the masonry

Visually

After installation

Caulking with thermally insulating material sealed with sealant. Covering with a solution of the junctions of blocks with masonry

Visually

After installing the box

Gap between floor surface and door leaf

With a steel meter

After installing the box

Installation of window sills

The presence of teardrops in wooden window sills

Visually

Before installation of window sills

Antiseptic and insulation of the bottom board surface wooden window sills

Visually

Before installation of window sills

Window sill slope

With the help of a rail, level, steel meter

After installing window sills

Overlay on the wall of the platband

With the help of a steel subway

Introduction
Regulatory documents regulating the quality of construction and installation works, building materials, products and structures
Test methods and quality control of building materials, products and structures during construction and installation works
Part 1. Construction work
A. Earthworks
1. Development of recesses (trenches) for structures
2. Development of pits with excavators
3. Development of trenches for pipelines in non-rocky soils
4. Backlink
5. Vertical layout
6. The device of embankments
B. Construction of foundations
7. Installation of blocks of strip foundations
8. Installation of blocks of walls of the underground part of buildings
9. Installation of glass-type foundation blocks
10. Device pile foundations
11. The device of prefabricated grillages
12. The device of monolithic grillages
13. Device for horizontal waterproofing of foundations from cement mortars
B. Concrete work
14. Installation of inventory formwork
15. Reinforcing work
16. Laying concrete mixtures
17. Installation of monolithic concrete and reinforced concrete walls
18. Installation of monolithic concrete and reinforced concrete columns
19. Installation of monolithic concrete and reinforced concrete foundations
D. Stone work
20. Wall laying
21. Laying partitions
22. Pillar laying
D. Installation work
23. Installation of reinforced concrete columns of one-story buildings
24. Installation of prefabricated reinforced concrete columns of multi-storey buildings
25. Installation of reinforced concrete crossbars, beams, trusses
26. Installation of floor slabs and coatings
27. Mounting flights of stairs and venues
28. Installation of balcony slabs and lintels
29. Installation of outdoor wall panels frame buildings
30. Installation of panels, blocks bearing walls buildings
31. Installation of volumetric blocks of elevator shafts
32. Installation of prefabricated reinforced concrete ventilation blocks
33. Installation of volumetric blocks
34. Installation of sanitary cabins
35. Installation of gypsum concrete partitions
36. Installation of asbestos-cement extrusion panels and plates
37. Installation of frame-sheathing partitions
38. Installation of walls from "Sandwich" type panels and sheet assembly
39. Welding field joints of reinforced concrete structures
40. Corrosion protection of steel embedded products
41. Sealing joints
42. Monolithic joints and seams
43. Garbage chute device
E. Roofing and insulation works
44. Preparation of foundations and underlying elements of insulation and roofing
45. Thermal insulation device from bulk materials
46. ​​The device of thermal insulation from plates
47. Insulation device from roll materials
48. Insulation device from polymer and emulsion-bitumen compositions
49. Roofing from roll materials
50. Roofing from piece materials
51. Roofing from polymer and emulsion-bitumen compositions
52. Metal roofing
G. Carpentry
53. Installation of window blocks
54. Installation of door blocks
55. Arrangement of mezzanines, cabinets
H. Flooring
56. Preparation of soil bases for floors
57. Installation of a concrete underlayment, screeds
58. Floor soundproofing device
59. Installation of glued floor waterproofing
60. Device bituminous waterproofing gender
61. The device of monolithic coatings
62. The device of floors from ceramic tiles
63. Arrangement of mosaic floors
64. Installation of floors made of polymeric materials
65. Laying logs in floors on floor slabs
66. Laying logs on posts on a dirt base
67. Arrangement of plank floors
68. The device of floors from block parquet
69. Arrangement of floors from panel parquet
AND. Finishing work
70. Plaster work (simple plaster)
71. Plaster work (improved plaster)
72. Plastering (high quality plaster)
73. Plastering works (coatings from sheets of dry gypsum plaster)
74. Painting works(coloring with water compositions)
75. Painting work (painting with anhydrous compounds)
76. Facing work
77. Wallpaper work
78. Glazing works (glazing of bindings)
79. Glass works (installation of glass blocks and glass panels)
80. Installation of glass profile fences
81. Finishing (facing) of walls with panels, sheets with factory finish
82. Installation suspended ceilings in building interiors
K. Landscaping
83. Drainage device
84. The device blind area of ​​concrete and asphalt concrete
85. The device of sidewalks and paths from plates
86. Device of crushed stone base and asphalt concrete pavement
Part 2. Repair and construction work
1. Repair and strengthening of old foundations
2. Laying of prefabricated reinforced concrete floor slabs during the reconstruction of brick buildings
3. The device of monolithic sections in the ceilings
4. Installation of floor slabs according to metal beams
5. Strengthening brick pillars and piers
6. Installation of metal jumpers
7. Installation of stairs on metal stringers
8. The device of the truss system of wooden elements
9. Repair plaster
10. Repair of plaster facades of buildings
11. Painting of facades
12. Installing facade moldings
13. Installation of downpipes
Part 3. Installation work
1. The device of holes and furrows for laying pipelines
2. Installation of cast iron pressure pipelines
3. Installation of pressure pipelines from asbestos-cement pipes
4. Installation of pipelines for internal cold and hot water supply
5. Installation of reinforced concrete and concrete non-pressure pipelines
6. Installation of sewer pipelines from ceramic pipes
7. System installation internal sewerage and drain
8. Installation of water fittings
9. Bathtub and washbasin installation
10. Installation of sanitary appliances
11. Installation of the internal heating system
12. Installation of metal air ducts
13. Electric lighting device
14. Arrangement of round reinforced concrete wells
15. Installation of chambers of heating mains
16. Installation of impassable channels
17. Insulation of pipelines of heating mains

1.23. Operational quality control should be carried out during construction processes or production operations and ensure the timely detection of defects and the adoption of measures to eliminate and prevent them.

1.24. Operational control performer checks:

Compliance of the sequence and composition of the technological operations performed with the technological and regulatory documentation applicable to these technological operations;

Compliance with technological regimes established by technological maps and regulations;

Compliance of quality indicators of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations

The results of operational control should be documented.

(12-01-2004, clause 6.1.6)

1.25. The executors of operational control are the foremen, foremen and workers of construction laboratories, geodetic and other services of the construction organization, as well as representatives of the customer and the design organization.

The results of the operational quality control are recorded in the journals or in Section 4 of the "General Journal of Work" (Appendix 3)

1.26. During the construction process, an assessment should be made of the performance of work, the results of which affect the safety of the facility, but, in accordance with the accepted technology, become unavailable for control after the start of subsequent work, as well as completed building structures and sections of engineering networks, the elimination of defects of which, identified by control, is impossible without dismantling or damaging subsequent structures and sections of engineering networks. Representatives of the relevant bodies of state supervision, architectural supervision, as well as, if necessary, independent experts may participate in these control procedures. The executor of the works not later than three working days notifies the other participants about the timing of the specified procedures.



The results of the acceptance of work hidden by subsequent work, in accordance with the requirements of the design and regulatory documentation, are documented in certificates of examination of hidden work (Appendix 12). The builder (customer) may require a re-examination after the elimination of the identified defects.

(12-01-2004, paragraphs 6.2, 6.2.1)

Acceptance control

1.27. To the procedure for assessing the conformity of individual structures, tiers of structures (floors), the performer of the work must submit certificates of examination of all hidden works that are part of these structures, geodetic executive schemes, as well as test reports for structures in cases provided for by design documentation and (or) a building contract . The developer (customer) can perform verification of the reliability of executive geodetic schemes presented by the contractor. To this end, the performer of the work must keep the alignment axes and mounting landmarks fixed in kind until the acceptance is completed.

The results of acceptance of individual structures must be documented in acts of acceptance of critical structures (Appendix 13).

1.28. The manual provides forms of certificates of examination of covert work on the acceptance of critical structures.

The list of hidden works and critical structures is determined by the design documentation.

1.29. When erecting complex and unique objects, certificates of examination of hidden works for the acceptance of critical structures should be drawn up taking into account the special instructions and technical conditions of the project documentation.

1.30. In accordance with clause 4.4 of the chapter of SNiP 3.01.03-84, the design organization must also determine the list of critical structures and parts of the structure subject to executive geodetic survey when performing acceptance control.

1.31. Examination of concealed works and intermediate acceptance of critical structures is carried out by commissions with the mandatory participation of representatives:

bridge building department

technical supervision of the customer;

· Design organizations - when accepting critical structures and concealed works provided for by the contract for architectural supervision.

1.32. Inspection and acceptance of works under clause 1.31 is carried out as they are ready. The bridge building division is obliged to call in advance representatives of the technical supervision of the customer and design organizations.

1.33. Certificates of inspection of hidden works and acceptance of critical structures are drawn up in two copies and, after signing, are kept by the contractor and the customer.

1.34. Until the acceptance of hidden work, it is prohibited to carry out subsequent work. It is also prohibited to load completed critical structures of bridges and pipes with construction and operational loads until the acceptance certificate for these structures is issued.

1.35. The following documentation must be submitted during acceptance control:

Executive drawings with introduced (if any) deviations or changes and documents on their agreement with design organizations-developers of drawings;

· factory technical passports, certificates, acts of acceptance by the factory inspection for steel, reinforced concrete and wooden structures;

· certificates or passports certifying the quality of materials used in the production of construction and installation works;

certificates of examination of hidden works;

acts of intermediate acceptance of structures;

Executive geodetic schemes of the position of structures;

work logs;

documents on quality control of welded joints;

acts of testing structures (if tests are provided for by working drawings);

other documents specified in the working drawings.

(3.03.01-87, paragraph 1.22)

Technical Supervision

1.36. The technical supervision of the developer (customer) of the construction is carried out by:

Checking that the contractor has quality documents (certificates in established cases) for the materials, products and equipment used by him, documented results of input control and laboratory tests;

Control over compliance by the performer of works with the rules for warehousing and storage of materials, products and equipment used; if violations of these rules are detected, the technical supervision representative may prohibit the use of improperly stored and stored materials;

· control of compliance of the operational control performed by the contractor with the requirements of SNiP 12-01-2004, clause 6.1.6.

· control of the availability and correctness of the maintenance of as-built documentation by the contractor, including the assessment of the reliability of geodetic executive schemes of the completed structures with selective control of the accuracy of the position of the elements;

control over the elimination of defects in the design documentation identified during the construction process, documented return of defective documentation to the designer, control and documented acceptance of the corrected documentation, its transfer to the contractor;

control over the execution by the contractor of the instructions of the state supervision bodies and local government;

· notification of state supervision authorities about all cases of emergency at the construction site;

· control of compliance of volumes and terms of performance of works with the terms of the contract and the calendar plan of construction;

assessment (together with the work contractor) of the compliance of the work performed, structures, sections of engineering networks, signing of bilateral acts confirming compliance; control over the fulfillment by the contractor of the work of the requirement on the inadmissibility of performing subsequent work until the signing of these acts;

final assessment (together with the work contractor) of the compliance of the completed construction facility with the requirements of legislation, design and regulatory documentation.

To carry out technical supervision, the developer (customer), if necessary, forms a technical supervision service, providing it with design and necessary regulatory documentation, as well as control and measuring devices and tools.

1.37. In cases provided for by law, the developer of project documentation carries out architectural supervision of construction. The procedure for implementation and functions of architectural supervision are established by the relevant regulatory documents.

The remarks of the representatives of the technical supervision of the developer (customer) and architectural supervision are documented. The facts of elimination of defects according to the comments of these representatives are documented with their participation.

(12-01-2004, paragraphs 6.4, 6.5)

1.38. Architectural supervision is carried out on the basis of an agreement (regulatory document) and is carried out, as a rule, during the entire period of construction and commissioning of the facility, and, if necessary, the initial period of its operation.

(SP 11-110-99, paragraphs 4.1,4.2)

1.39. When exercising architectural supervision over the construction of an object, a journal of architectural supervision of construction (hereinafter referred to as the journal) is regularly maintained, which is compiled by the designer and transferred to the customer. Forms for filling out the journal are given in Appendix 5.

(SP 11-110-99, clause 5.1)

1.40. Logging can be carried out both for the construction site as a whole, and for its start-up complexes or individual buildings and structures.

The design of the journal should be carried out in accordance with GOST 2.105-95. The journal must be laced, numbered, decorated with all signatures on the title page and sealed with the customer's seal. The magazine is transferred by the customer to the contractor and is located at the construction site until it is completed. The journal is filled in by the head or specialists exercising architectural supervision, the customer and an authorized person of the contractor.

After construction is completed, the contractor hands over the magazine to the customer.

Each visit to the construction site by specialists is recorded in the journal.

Records and instructions of specialists are set out clearly, with the necessary references to the current building codes and the rules state standards, specifications.

(SP 11-110-99, paragraphs 5.1-5.5)

1.41. Representatives of state control (supervision) bodies, upon notification of the contractor, may participate, in accordance with their authority, in the procedures for assessing the conformity of the results of work hidden by subsequent work and individual structures.

(12-01-2004, item 6.9)

1.42. When discrepancies are identified, the state control (supervision) bodies apply the sanctions provided for by the current legislation.