Operational control of construction and installation works. Cards of operational quality control of the main construction and installation works
11.9.1 During the performance of production processes and operations, operational control is carried out in order to identify defects that may be hidden during the continuation of the process or operation, and to take measures to prevent and eliminate these defects.
11.9.2 By operational control, the person carrying out the construction checks:
Compliance with the sequence and composition of the technological operations performed by the technological and regulatory documentation applicable to these technological operations;
Compliance with the technological regimes established technological maps and regulations;
Compliance of the quality indicators of the performance of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations.
11.9.2 During the construction process, an assessment of the work performed, the results of which affect safety, should be carried out. object, but in accordance with the accepted technology, they become unavailable for control after the start of the subsequent work, as well as the completed building structures and sections of engineering networks, the elimination of defects of which, identified by the control, is impossible without dismantling or damaging subsequent structures and sections of engineering networks. Representatives of the relevant bodies of state supervision, architectural supervision, as well as, if necessary, independent experts may participate in these control procedures. The performer of works not later than three working days notifies the other participants about the timing of the specified procedures.
11.9.3 The results of the acceptance of work hidden by subsequent work, in accordance with the requirements of the design and regulatory documentation, are documented in certificates of survey of hidden work ( Annex M ). The builder (customer) may require a re-examination after the elimination of the identified defects.
11.9.4 To the procedure for assessing the conformity of individual structures, tiers of structures (floors), the performer of the work must submit certificates of survey of all hidden works that are part of these structures, geodetic executive schemes, as well as test reports for structures in cases provided for by the design documentation and (or) building contract. The developer (customer) can perform verification of the reliability of the executive geodetic schemes submitted by the contractor. To this end, the performer of the work must keep, until the completion of the acceptance, the alignment axes and mounting landmarks fixed in kind.
The results of acceptance of individual structures should be documented in acts of acceptance of critical structures ( annex H ).
11.9.5 Tests of sections of engineering networks and installed engineering equipment are carried out in accordance with the requirements of the relevant regulatory documents and are documented in acts of acceptance of critical structures (Appendix H).
11.9.6 If, as a result of phased acceptance, defects in works, structures, sections of engineering networks are detected, the relevant acts should be drawn up only after the identified defects have been eliminated.
In cases where subsequent work must begin after a break of more than 6 months from the moment the phased acceptance is completed, these procedures should be repeated before the resumption of work with the execution of the relevant acts.
11.9.7 Places for performing control operations, their frequency, performers, methods and measuring instruments, forms for recording results, decision-making procedures in case of detection of non-compliance with established requirements must comply with the requirements of design, technological and regulatory documentation.
11.9.8 The person carrying out the construction appoints by its administrative documents responsible executors for the performance of operational control, documentation of its results and elimination of defects identified by the control.
The results of operational control should be documented in special work logs.
Design and Technological Institute of Industrial Construction
OJSC PKTIpromstroy
CHARTS OF OPERATIONAL QUALITY CONTROL OF MAIN CONSTRUCTION AND ASSEMBLY WORKS
1. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF REINFORCED CONCRETE COLUMNS 2. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF LARGE-BLOCK TAPE FOUNDATIONS 3. OPERATIONAL CONTROL CHART DURING INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS 4. OPERATIONAL CONTROL CHART DURING INSTALLATION OF CAMs 5. OPERATIONAL CONTROL CHART OF THE INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS 6. CHART OF OPERATIONAL CONTROL OF THE INSTALLATION OF FLOOR PANELS (COATINGS) 7. OPERATIONAL CONTROL CHART FOR WALL FORMWORK INSTALLATION 8. OPERATIONAL CONTROL CHART INSTALLATION OF FORMWORK COLUMNS AND FLOORS 9. OPERATIONAL CONTROL CHART WHEN INSTALLING THE FOUNDATION FORMWORK 10. KAPTA OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT 11. CHART OF OPERATIONAL CONTROL OF CONCRETING SLABS 12. WALL CONCRETING OPERATIONAL CONTROL CHART 13. COLUMN CONCRETING OPERATIONAL CONTROL CHART 14. OPERATIONAL CONTROL CARD FOR BRICK PILLARS 15. OPERATIONAL CONTROL CARD FOR BRICK WALLS 16. OPERATIONAL CONTROL CHART INSTALLATION OF WINDOW AND DOOR UNITS |
1. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF REINFORCED CONCRETE COLUMNS
Tolerances for the installation of reinforced concrete columns in accordance with the requirements of SNiP 1. Difference in elevations of the tops of adjacent columns or support platforms (brackets, consoles) ± 10mm 2. Difference in elevations of the tops of columns or support platforms within the area to be verified: with a contact installation 12 + 2, where - serial number of the tier when installed on beacons 10 mm 3. Offset of the axes of the columns of one-story buildings in the upper section from the vertical at the height of the columns H: in meters up to 10 m ± 10 mm over 10 m 0.001 N, but not more than 35 mm 4. Offset of the axes of the columns multi-storey buildings in the upper section relative to the center lines for columns with a height of up to 4.5 m ± 10 mm over 4.6 m ± 15 mm
Table 1
Operations subject to control |
Composition of control |
Control method |
Control time |
Works |
Activated works |
Work Producer |
Preparatory work |
Proper warehousing |
Visually |
Before installation |
Elevation of the bottom of the foundation glass |
With the help of a level |
Before installation |
Surveyor |
Installation of columns |
Reliability of slinging, verticality of installation, alignment; marks of reference platforms; temporary fastening |
Visually; with the help of a level; using a theodolite |
During installation |
Surveyor |
Welding of metal parts |
Weld quality |
Visually |
During installation |
Anti-corrosion protection of metal parts |
Visually |
During installation |
If necessary, the laboratory |
Casting columns |
Carefulness of monolithic |
Visually |
During installation |
Preparatory work(reception of designs) |
Availability of passports, drawings, geometric dimensions, external defects, drawing of center axes, marks, dimensions of support areas, correct location of embedded parts |
Visually; with a steel meter |
Before installation |
Preparation of column installation sites |
Cleaning glasses, dimensions of the foundation glass; the presence of risks on the foundation |
Before installation |
Mounting hardware installation |
Fixture fixing accuracy |
Visually |
During installation |
Welding of metal parts |
Compliance with the project; welding of electrodes; seam dimensions |
Visually |
During installation |
Laboratory |
Embedding columns in foundations |
Grade, consistency of concrete mix, thoroughness of compaction |
Visually, using a standard cone |
During installation |
Laboratory |
2. OPERATIONAL CONTROL CHART DURING THE INSTALLATION OF LARGE-BLOCK TAPE FOUNDATIONS
Tolerances for the installation of large-block strip foundations in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of foundation blocks and blocks of foundation walls relative to the center axes ± 10 mm 2. Deviation of the marks of the upper supporting surfaces of the foundation elements - 10 mm 3. Displacement of axes or faces wall blocks in lower section relative to the center axes or geometric axes below installed structures± 5mm
table 2
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Determining the state of soils |
Visually |
Before installation |
The correct location of the pit relative to the layout drawing, the reliability of fastening, the elevation of the bottom of the pit |
Visually, using a level and tape measure |
Before installation |
Surveyor |
Marking the top of a sand or gravel pad |
With the help of a level |
Before installation |
Surveyor |
Proper warehousing |
Visually |
Before installation |
Breakdown of axes of foundations |
The accuracy of determining the position of the corners of the building. Compliance with the project of distances between the axes of prefabricated foundations |
With theodolite and tape measure |
Before installation |
Surveyor |
Installation of foundation blocks |
Visually |
During installation |
Accuracy of installation, foundation blocks. Density of support and abutment |
With level and plumb |
During installation |
Compliance of marks with design |
With the help of a level |
After installing the blocks |
Surveyor |
Preparatory work |
Sufficiency of the sizes of pits |
With the help of a tape measure |
Before installation |
The thickness of the sand or gravel cushion, the quality of its compaction |
Visually, using a steel meter |
Before installation |
Cleaning foundation blocks from dirt, from snow in winter |
Visually |
Before installation |
Availability of passports for reinforced concrete structures; correspondence of the geometric dimensions of the blocks to the project; external defects |
Roulette |
Before installation |
Breakdown of foundation axes |
The correctness of the tension of the axes, the accuracy of the intersection of the axes on the foundation blocks |
With a theodolite |
Before installation |
Surveyor |
Installation of foundation blocks |
Compliance with installation technology, Technological map |
Visually |
During installation |
3. OPERATIONAL CONTROL CHART DURING INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS
Tolerances during the installation of reinforced concrete foundations for columns in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of the foundation cups relative to the center axes ± 10mm 2. Deviation of the marks of the upper supporting surfaces of the foundation elements - 10mm 3. Deviation of the bottom marks of the foundation cups - 20mm
Table 3
Operations subject to control |
Composition of control |
Control method |
Control time |
Activated works |
Work Producer |
Preparatory work |
Preparation of the base for foundations, its condition, dimensions, marks, protection against freezing in winter |
With the help of a level, steel meter, tape measure |
Before installation |
Surveyor |
The dimensions of the pits, the correctness of their location and the reliability of fastening the walls of the pit, the marks of the bottom of the pit |
Visually, using a level, tape measure, plumb line |
Before installation |
Base top elevation and cushion levelness |
With the help of a level |
Before installation |
Surveyor |
Lateral waterproofing of foundation blocks |
Insulation quality |
Visually |
After installation |
Preparatory work |
The thickness of the sand or gravel pad and the quality of its compaction |
Visually i with a steel meter |
Before installation |
Cleaning from dirt, in winter from snow and ice |
Visually |
Before installation |
Checking the geometric dimensions of blocks, defects. Comparison of passport data of reinforced concrete structures with design |
Before installation |
Installation of control sights along the axes of the foundations |
Compliance with the design of the axles transferred to the bottom of the pit. The accuracy of the position of the top of the control sights |
With the help of a theodolite, a level |
Before installation |
Installation and alignment of blocks |
Installation accuracy, compliance with design marks and axes |
With the help of a level |
During installation |
Surveyor |
4. OPERATIONAL CONTROL CHART DURING INSTALLATION OF CAMs
Tolerances for the installation of crossbars in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of the crossbars along the lower belt relative to the geometric axes of the supporting structures ± 6 mm 2. Deviation of the distances between the axes of the crossbars at the level of the upper chords ± 20mm 3. The tolerances of the support areas and the tolerances of the gaps between the elements are determined by the project
Table 4
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Proper storage of structures |
Visually |
Before installation |
Alignment of bearing surfaces on columns |
Correspondence of the marks of the supporting platforms of the columns with the design ones, the correctness of the marking axes |
With the help of a theodolite, level, steel meter |
Before installation |
Surveyor |
Installation of crossbars |
Correctness and reliability of slinging |
Visually |
During installation |
Alignment of the axes of the crossbar with the center axes on the supporting structures, the verticality and density of the support of the crossbar |
Visually, with a plumb line |
During installation |
Welding of embedded parts in joints |
Visually, using a steel meter |
During installation |
If necessary, the laboratory |
Sealing joints |
External type of joints, strength of concrete at the joint |
Visually, using a reference hammer |
After stripping the joint |
Laboratory |
Preparatory work |
Compliance of the geometric dimensions with the design ones, external defects, the presence of passports, the correct location of embedded parts, their cleaning |
Visually, using a steel meter, tape measure |
Before installation |
Alignment of bearing surfaces on columns |
Visually, using a steel meter |
Installation of crossbars |
Correctness of drawing axial and control marks on crossbars |
Visually, using a steel meter, tape measure |
During installation |
Visually |
During installation |
Compliance with the design of the joint and the brand of electrodes according to the project |
Visually |
During installation |
Sealing joints |
The density and strength of the formwork |
Visually |
During installation |
Before concreting |
Laboratory |
Joint seal quality |
Visually |
During the concreting process |
Joint filling quality |
Visually |
After stripping |
5. OPERATIONAL CONTROL CHART OF THE INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS
Tolerances for the installation of reinforced concrete trusses and beams in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of trusses (beams) along the lower chord relative to the geometric axes of the supporting structures ± 5mm 2. Deviation of the distances between the axes of trusses (beams) at the level of the upper chords ± 20 mm 3. Tolerances of support areas and tolerances of gaps between elements are determined by the project
Table 5
Quality Control Persons |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Proper storage of reinforced concrete structures |
Visually |
Before installation |
Alignment of supporting surfaces of previously assembled structures |
Compliance of the marks of the reference platforms with the design ones, the correctness of the marking axes |
Before installation |
Surveyor |
Installation of trusses, beams |
Correctness and reliability of slinging |
Visually |
During installation |
Alignment of beam truss axes with center axes, verticality of support structures |
Visually, with a plumb line |
During installation |
Reliability of temporary fastening |
Visually |
During installation |
Welding of embedded parts in joints |
Quality of welding, certificates of acceptance of welded joints, dimensions of welds |
Visually, using a steel meter |
In the process of installation |
Anti-corrosion protection |
The quality of the application of the anti-corrosion layer |
Visually |
Before monolithic |
If necessary, the laboratory |
Preparatory work |
Availability of passports, geometric dimensions, external defects, reinforced concrete structures |
Visually, using a steel meter |
Before installation |
The location of embedded parts, cleaning them from rust and concrete sagging |
Visually, using a steel meter |
Before installation |
Alignment of supporting surfaces of structures |
The position of the support pads and embedded parts |
Visually |
Before installation |
Installation of beam trusses |
Presence and correctness of drawing axial and control marks on structures |
With a steel meter |
During installation |
Correct installation technology |
Visually |
During installation |
Welding of embedded parts in joints |
Type of electrodes, joint compliance with the project |
Visually |
During installation |
Sealing joints |
The density and strength of the formwork |
Visually |
Before concreting |
Concrete grade, compaction quality |
Visually |
In the process of monolithic |
Laboratory |
The appearance of the joint, the quality of the seal |
Visually |
In the process of monolithic |
Compliance of the marks of the installed structures with the design ones, the distance between the axes |
Visually |
After installation |
Surveyor |
6. CHART OF OPERATIONAL CONTROL OF THE INSTALLATION OF FLOOR PANELS (COATINGS)
Tolerances for the installation of floor panels (coverings) in accordance with the requirements of SNiP III -16-73 1. The difference in elevations of the front surfaces of two adjacent floor slabs (coverings) at the joint ± 5 mm supporting surfaces and truss nodes and other load-bearing structures(along the supporting sides of the slabs), not allowed 3. Permissible deviations in the dimensions of the support areas and gaps between structural elements are determined by the project
Table 6
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved with control |
Activated works |
Work Producer |
Preparatory work |
Proper stacking of panels |
Visually |
Before installation |
Compliance of marks and support sites with design |
With the help of a level, tape measure, steel meter |
Before installation |
Surveyor |
Installation of floor panels |
Instrumental check of the installation horizon of each floor |
With the help of a level |
During installation |
Surveyor |
Anti-corrosion protection of anchors |
The quality of the anti-corrosion coating |
Visually |
Fastening joints |
Laboratory |
Sealing joints |
The quality of the monolithic joints |
Visually |
After monolithic |
Preparatory work |
Availability of passports, geometrical changes, surface quality of structures |
Before installation |
Correct location of embedded parts, mounting loops |
Visually, using a tape measure, a steel meter |
Before installation |
Execution of the supporting row of brickwork by poking |
Visually |
Before installation |
Mortar bed making |
Correspondence of the grade of mortar to the project, the thickness of the mortar layer |
Visually |
During installation |
Laboratory |
Panel mounting |
Compliance with the area of support, the position of the panel in plan, the density of contact with the supporting surface, the correct installation technology |
Visually |
During installation |
Panel anchoring |
Compliance of anchoring with project requirements |
Visually |
Before monolithic |
Sealing joints |
Cleaning and moistening of the surfaces to be joined, compliance of the brand of mortar or concrete with the design ones |
In the process of monolithic |
Laboratory |
7. OPERATIONAL CONTROL CHART FOR WALL FORMWORK INSTALLATION
Tolerances when installing wall formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design slope of the wall formwork planes and their intersection lines with wall heights up to 5 m 10 mm with wall heights over 5 m 15 mm 2. Offset of wall formwork axes : from the design position 8 mm 3. Internal dimensions of the wall formwork from the design dimensions 3 mm 4. Local irregularities of the formwork when checking with a two-meter rail 3 mm
Table 7
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Visually |
Before formwork installation |
Formwork installation |
After installing the wall formwork (before it is fixed) |
Surveyor |
Accuracy of installation of embedded parts, their fastening |
With the help of a meter, tape measure |
After installing the formwork |
Preparatory work |
Compliance with the project and the quality of formwork panels, correct storage |
Visually, with a meter |
Before formwork installation |
Formwork installation |
Compliance with design dimensions, verticality |
With the help of a meter, a plumb line |
During formwork installation |
Formwork fixing quality |
Visually |
During formwork installation |
The quality of the inner surface of the formwork |
During formwork installation |
8. OPERATIONAL CONTROL CHART INSTALLATION OF FORMWORK COLUMNS AND FLOORS
Tolerances for the installation of the formwork of columns and ceilings in accordance with the requirements of SNiP III -15-76 1. The distance between the supports of the bent formwork elements and the distance between the ties of the vertical supporting structures from the design dimensions: per 1 m of length 25 mm for the entire span at least 75 mm 2. Distance from the vertical or the design slope of the formwork planes and their intersection lines: by 1 m of height 5 mm for the entire height of columns up to 5 m 10 mm - "- more than 5 m 15 mm for the entire height of the beams 5 mm 3. Displacement of the formwork axes from the design position of the columns 8 mm - "- beams 10 mm 4. The distance between the inner surfaces of the formwork of columns, beams from the design dimensions - 3 mm 5. Local irregularities of the formwork when checking with a 2-meter rail - 3 mm
Table 8
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Determination of the state of the base (for columns) |
Visually |
Before formwork installation |
Formwork installation |
Compliance of supporting scaffolding and scaffolding with the project, their stability and rigidity |
Visually, using a steel meter, tape measure, plumb line |
Before formwork installation |
Correspondence of the formwork position to the installation axes |
Using a theodolite, plumb line, tape measure |
During formwork installation |
Surveyor |
Installation accuracy of embedded parts |
With a steel meter, tape measure |
Formwork Ambassador |
Preparatory work |
The quality of formwork panels and fasteners |
Visually, using a steel meter |
Before formwork installation |
Proper storage of formwork elements |
Visually |
Before formwork installation |
Formwork installation |
Compliance with design dimensions and marks |
With the help of a level, plumb line, level, steel meter, tape measure |
During formwork installation |
Formwork surface quality (density at the interface of boards) |
Visually, using a 2-meter rail |
During formwork installation |
Formwork fastening quality |
Visually |
During formwork installation |
9. OPERATIONAL CONTROL CHART WHEN INSTALLING THE FOUNDATION FORMWORK
Tolerances when installing the foundation formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design position of the foundation formwork planes and lines of their intersections per 1 m height 5mm 2. Offset of foundation formwork axes from the design position of 15mm foundations for steel structures , (L - length of the span or step of the structure, m) 3. Local irregularities of the formwork (when checking with a rail 2 m long) 3 mm
Table 9
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Determination of the state of the base |
Visually |
Before formwork installation |
Formwork installation |
Compliance with the position of the formwork to the installation axes, the accuracy of the installation of embedded parts and their fastening |
With the help of a theodolite, tape measure, plumb line, steel meter |
After installing the formwork |
Surveyor |
Preparatory work |
Compliance with the design and quality of formwork panels, blocks and fasteners, correct storage of formwork elements |
Visually, using a steel meter |
Before formwork installation |
Formwork installation |
Compliance with design dimensions and marks. Horizontal and vertical formwork elements, quality of fasteners, quality of the inner surface of the formwork |
Visually, using a level, plumb line, steel meter |
During formwork installation |
10. KAPTA OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT
Tolerances for reinforcement of structures in accordance with the requirements of SNiP III -15-76 1. Reinforcing steel supplied for construction must be subjected to external inspection upon acceptance. measurements and control tests in cases stipulated in the project 2. The replacement of the reinforcing steel provided for by the project is agreed with the design organization 3. Before mounting the reinforcement, the formwork is checked, the linings are fixed, providing a gap for the protective layer equipment 4. The mounted reinforcement is fixed from displacement and protected from damage during concreting 5. The displacement of reinforcing bars when they are installed in the formwork should not exceed 1/5 of the largest diameter of the bar and 1/4 of the diameter of the installed barTable 10
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Reinforcement acceptance |
Compliance of reinforcing meshes and frames with the project (passport) |
Visually |
Before installation |
Reinforcement installation |
Installation of grids, frames, embedded parts in accordance with the project |
With the help of a plumb line, a steel meter |
During installation |
Providing a protective layer |
With a steel meter |
When installing formwork |
Fixing joints, frames, meshes (welding, knitting) |
Visually |
After fixing |
Laboratory |
Reinforcement acceptance |
It is carried out selectively The diameter of the reinforcement, the distance between the working rods in meshes and frames are checked |
With a caliper and a steel meter |
Before installation |
Embedded parts position |
With a steel meter |
Before installation |
The quality of the reinforcement fastening points in the mesh frame |
Visually |
Before installation |
Armature storage |
Proper warehousing and storage |
Visually |
Before installation |
Correct slinging |
Visually, using a steel meter |
During installation of fittings |
Reinforcement installation |
Compliance with the technology adopted in the technological map or commissioning |
Visually |
During installation of fittings |
The correct layout of the grids, the correct fixing of the reinforcement in the formwork |
Visually, using a steel meter |
During installation of fittings |
Correct installation of running boards on the slab |
Visually |
During installation of fittings |
11. CHART OF OPERATIONAL CONTROL OF CONCRETING SLABS
Tolerances for concreting floors in accordance with the requirements of SNiP III -15-76 1. Local deviations of the concrete surface from the design when checking structures with a rail 2 m long ± 5 mm 2. In the marks of surfaces and embedded parts that serve as supports for metal or precast concrete elements ± 5 mm 3. In the location of anchor bolts, in plan inside the contour of the support - 5 mm in plan outside the contour of the support - 10 mm 4. Difference of marks in height at the junction of two adjacent surfaces - 3 mm
Table 11
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Formwork quality |
Visually |
Before concreting |
Condition of reinforcement and embedded parts, act of acceptance of reinforcement |
Visually |
Before concreting |
Stripping |
Surface quality, compliance with the design of holes, geometric dimensions |
Visually, with a meter |
After stripping |
The strength of concrete, its uniformity, the presence of cracks |
Visual, ultrasonic device |
After stripping |
Laboratory |
Preparatory work |
Base quality, removal of the top layer during working seams, notching, washing |
Visually |
Before concreting |
Concrete laying |
The quality of the concrete mix |
With the help of the StroyTsNIIL cone, the press |
Before concreting |
Laboratory |
Visually |
During installation |
Visually |
During installation |
Outside temperature |
With a thermometer |
During installation |
Concrete compaction |
Transposition step and immersion depth of vibrators |
Visually |
During compaction |
Sufficiency of vibration and thickness of the concrete layer during compaction |
Visually |
During compaction |
Curing concrete care |
With a thermometer |
During the curing process |
12. WALL CONCRETING OPERATIONAL CONTROL CHART
Tolerances for concreting walls in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or design slope to the full height: walls supporting monolithic coatings and floors ± 15mm walls supporting precast beam structures ± 10mm 2. Horizontal planes on the entire plane of the verified area ± 20mm 3. Local deviations of the concrete surface from the design when checking the structure with a rail 2 m long ± 5 mm 4. In the marks of surfaces and embedded parts - 5 mm
Table 12
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Formwork quality |
Visually |
Before concreting |
Compliance with the design elevation of the base |
With the help of a level |
Before concreting |
Surveyor |
Condition of fittings and embedded parts, act of acceptance of fittings |
Visually |
Before concreting |
Stripping |
Surface quality, compliance with the design of holes, openings, channels, geometric dimensions |
Visually, using a steel meter |
After stripping |
The strength of concrete, its uniformity, the presence of supports, cracks |
With the help of an ultrasonic device, visually |
After stripping |
Laboratory |
Preparatory work |
The quality of the base, the removal of the top layer at the working seams, notch, prominka, the presence of waterproofing |
Visually |
Before concreting |
Concrete laying |
The quality of the concrete mixture (mobility, cubic strength) |
Before concreting |
Laboratory |
The correctness of the technology of laying the concrete mix |
Visually |
During installation |
Correct execution of work seams |
Visually |
During installation |
Temperature of outdoor air and concrete mixture (in winter) |
With a thermometer |
During installation |
Concrete compaction |
Transposition step and immersion depth of vibrators |
Visually, using a steel meter |
During compaction |
Sufficiency of vibration and thickness of the concrete layer during laying |
Visually, using a steel meter |
During compaction |
Compliance with humidity and temperature conditions |
With a thermometer |
During the curing process |
13. COLUMN CONCRETING OPERATIONAL CONTROL CHART
Tolerances during concreting in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or from the design slope to the entire height of columns supporting monolithic coatings and floors ± 15 mm Same, for columns supporting precast beam structures ± 10 mm 2. Horizontal planes on the entire plane of the area to be verified ± 20 mm 3. Local deviations of the concrete surface from the design when checking structures with a rail 2 m long, except for supporting surfaces ± 6 mm 4. In the dimensions of the cross-section of elements + 6 mm - 3 mm 5. In the marks of surfaces and embedded parts that serve as supports for metal or precast concrete elements - 5 mm
Table 13
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons or units involved in control |
Activated works |
Work Producer |
Preparatory work |
Formwork quality |
Visually |
Before concreting |
Compliance with the design elevation of the base |
With the help of a level |
Before concreting |
Surveyor |
Condition of reinforcement, embedded parts, act of acceptance of reinforcement |
Visually |
Before concreting |
Stripping |
Determination of surface quality, compliance with the project of geometric dimensions, correct location of embedded parts, marks of the top of columns |
Visually, using a steel meter, level |
After stripping |
Surveyor |
Determination of the strength of concrete, its uniformity |
Using ultrasonic devices |
After stripping |
Laboratory |
Preparatory work |
Determining the quality of the base (cleaning from dirt, ice, snow, etc.) |
Visually |
Before concreting |
Concrete laying |
Determination of the quality of the concrete mixture (mobility, cubic strength) |
With the help of the StroyTsNIIL cone, press (PSU-500) |
Before laying in the structure |
Laboratory |
Compliance with concrete laying technology |
Visually |
During installation |
Concrete compaction |
Temperature control of outdoor air and concrete mix (in winter) |
With a thermometer |
During installation |
Compliance with the permutation step and the depth of immersion of the vibrators, the correctness of their installation |
Visually, using a steel meter |
During compaction |
Determination of vibration sufficiency and concrete layer thickness |
Visually, using a steel meter |
During compaction |
Concrete care during hardening |
Compliance with humidity and temperature conditions |
With a thermometer |
During the curing process |
Laboratory |
14. OPERATIONAL CONTROL CARD FOR BRICK PILLARS
Tolerances for masonry pillars in accordance with the requirements of SNiP III -17-78 1. Deviations from the design dimensions: 10mm in thickness, 10mm in marks of cutoffs and floors, 10mm in displacement of the axes of structures 10mm 2. Deviation of masonry surfaces and angles from the vertical: one floor 10mm 30mm for the whole building
Table 14
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
The correctness of the binding of poles to the center axes |
Visually, with a plumb line |
Before the start of laying |
Brickwork pillars |
Determination of the correct masonry technology and ligation of seams |
With the help of a plumb line, a steel meter, visually |
In the process of laying |
Determining the conformity of the actual position of the performed brick pillars project, alignment of pillars of different floors |
Visually, using a plumb line, steel meter |
In the process of laying |
Marking the edges of brickwork and floors, the correct arrangement of the pillow under the beams, the support of the beams on the pillows and their embedding in the masonry |
Visually, using a level, a steel meter |
After installing the pillow and installing the beam |
Surveyor |
Preparatory work |
Determination of the base for the pillars, the presence of waterproofing |
Visually |
Before pole laying |
Determination of the quality of bricks, reinforcement, embedded parts |
Visually, measuring, checking passports and certificates |
Before pole laying |
Laboratory |
Brickwork pillars |
Dimensions, filling and dressing of seams; |
With a steel meter |
After every 5 m of laying |
Geometric dimensions of the section of the pillars |
With a steel meter |
During the masonry process |
Verticality of masonry, unevenness on the surface |
With the help of a plumb line, rail, steel meter |
After the completion of the laying of the pillar to the height of the floor |
Masonry reinforcement |
The correct location of the reinforcement, the distance between the grids along the height of the column, the diameter of the rods and the distance between them |
With a steel meter, caliper |
As the reinforcement is laid |
15. OPERATIONAL CONTROL CARD FOR BRICK WALLS
Tolerances for masonry walls in accordance with the requirements of SNiP III -17-78 1. Deviation from design dimensions; by thickness 15 mm by marks of edges and floors 10 mm by width of piers 15 mm by width of openings 15 mm by displacement of axes of adjacent window openings 20 mm by the displacement of the axes of the structures 10 mm 2. Deviations of the surfaces and corners of the masonry from the vertical: one floor 10 mm for the entire building 30 mm 3. Deviations of the rows of masonry from the horizontal by 10 m in length 15 mm 4. Irregularities on the vertical surface of the masonry, detected when overlaying a 2-meter rail 10 mm
Table 15
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Brickwork walls. |
The quality of bricks, mortar, fittings, embedded parts |
External inspection, measurement, verification of passports and certificates |
Before the laying of the walls of the floor |
In case of doubt - laboratory |
The correctness of the breakdown of the axes |
With a steel tape measure, meter |
Before the start of laying |
Horizontal marks of masonry cutouts |
Using a level, staff.level |
Before installing floor panels |
Surveyor |
Alignment of ventilation ducts and sealing of ventilation units |
Visually, with a plumb line |
After finishing the laying of the walls of the floor |
Masonry reinforcement |
The correct location of the reinforcement, the diameter of the rods, etc. |
Visually, using a steel meter |
Before fittings |
Prefabricated installation reinforced concrete slabs floors |
Supporting floors on groans, embedding, anchoring |
Visually, using a steel meter |
After installing the cover |
Anti-corrosion coating of embedded parts |
Thickness, density and adhesion of the coating |
Visually, using a thickness gauge, engraving shchitel |
Before termination |
Laboratory |
Installation of balconies |
Seal, mark, slope of balconies |
Using a steel meter, level, 2-meter rail |
After installing balconies |
Brickwork walls |
Geometric masonry dimensions |
With a steel tape measure, meter |
Verticality, horizontality and masonry surface |
Using a level, rail, plumb |
During and after the laying of the walls of the floor |
Quality of masonry seams |
With steel meter, 2 meter rail |
After completing every 10m 3 masonry |
Breakdown and marks of the bottom of the openings |
With the help of a steel tape measure. level, level |
Before the start of laying the walls |
Removal of the mark + 1m from the finished floor |
With the help of a level |
After finishing the laying of the floor |
Apartment layout |
Visually |
After the start of laying the walls |
Geometric dimensions of the premises |
With steel tape measure |
After the start of laying the walls |
Jumper setting |
Jumper position, support, placement, termination |
Visually, using a steel meter |
After installing jumpers |
Installation landings |
Position of pistil areas, support, placement, incorporation |
Visually, using a steel meter |
After installing the platforms |
Welding of embedded parts |
Length, height, quality of welds |
Visually, by tapping with a hammer |
Before anti-corrosion coating |
Soundproofing device |
Construction, workmanship |
Visually |
Immediately after finishing work |
16. OPERATIONAL CONTROL CHART INSTALLATION OF WINDOW AND DOOR UNITS
Rules for installing window and door blocks in accordance with the requirements of SNiP III -19-76 1. Surfaces of window and door blocks adjacent to stone walls, antiseptic with waterproofing materials 2. Gaps between the frame and masonry of the outer walls are sealed with thermal insulation materials 3. Window and door frames in stone walls and partitions are fastened with screws or steel ruffs driven into wooden antiseptic corks. Each vertical bar of the box is fixed in at least 2 places, the distance between them does not exceed 1 meterTable 16
Quality Control Persons |
Operations subject to control |
Composition of control |
Control method |
Control time |
Persons involved in control |
Activated works |
Work Producer |
Preparatory work |
Appearance, factory readiness, compliance with standards, ENiP and the project, completeness of delivery of window and door units, availability of antiseptic acts |
Visually |
When accepting blocks |
The presence of antiseptic plugs for fastening blocks |
Visually |
Before block installation |
Conditions of transportation and storage |
Visually |
At the construction site |
Installation of door and window units |
Correct installation at a given elevation and along a given axis |
Using a level, plumb line, tape measure |
After installing the boxes |
Box fixing |
Visually |
After installing the boxes |
Density of fit of window and door frames |
Visually |
After installing the boxes |
Waterproofing of the junction of blocks to the masonry |
Visually |
After installation |
Caulking with thermally insulating material sealed with sealant. Covering with a solution of the junctions of blocks with masonry |
Visually |
After installing the box |
Gap between floor surface and door leaf |
With a steel meter |
After installing the box |
Installation of window sills |
The presence of teardrops in wooden window sills |
Visually |
Before installation of window sills |
Antiseptic and insulation of the bottom board surface wooden window sills |
Visually |
Before installation of window sills |
Window sill slope |
With the help of a rail, level, steel meter |
After installing window sills |
Overlay on the wall of the platband |
With the help of a steel subway |
Regulatory documents regulating the quality of construction and installation works, building materials, products and structures
Test methods and quality control of building materials, products and structures during construction and installation works
Part 1. Construction work
A. Earthworks
1. Development of recesses (trenches) for structures
2. Development of pits with excavators
3. Development of trenches for pipelines in non-rocky soils
4. Backlink
5. Vertical layout
6. The device of embankments
B. Construction of foundations
7. Installation of blocks of strip foundations
8. Installation of blocks of walls of the underground part of buildings
9. Installation of glass-type foundation blocks
10. Device pile foundations
11. The device of prefabricated grillages
12. The device of monolithic grillages
13. Device for horizontal waterproofing of foundations from cement mortars
B. Concrete work
14. Installation of inventory formwork
15. Reinforcing work
16. Laying concrete mixtures
17. Installation of monolithic concrete and reinforced concrete walls
18. Installation of monolithic concrete and reinforced concrete columns
19. Installation of monolithic concrete and reinforced concrete foundations
D. Stone work
20. Wall laying
21. Laying partitions
22. Pillar laying
D. Installation work
23. Installation of reinforced concrete columns of one-story buildings
24. Installation of prefabricated reinforced concrete columns of multi-storey buildings
25. Installation of reinforced concrete crossbars, beams, trusses
26. Installation of floor slabs and coatings
27. Mounting flights of stairs and venues
28. Installation of balcony slabs and lintels
29. Installation of outdoor wall panels frame buildings
30. Installation of panels, blocks bearing walls buildings
31. Installation of volumetric blocks of elevator shafts
32. Installation of prefabricated reinforced concrete ventilation blocks
33. Installation of volumetric blocks
34. Installation of sanitary cabins
35. Installation of gypsum concrete partitions
36. Installation of asbestos-cement extrusion panels and plates
37. Installation of frame-sheathing partitions
38. Installation of walls from "Sandwich" type panels and sheet assembly
39. Welding field joints of reinforced concrete structures
40. Corrosion protection of steel embedded products
41. Sealing joints
42. Monolithic joints and seams
43. Garbage chute device
E. Roofing and insulation works
44. Preparation of foundations and underlying elements of insulation and roofing
45. Thermal insulation device from bulk materials
46. The device of thermal insulation from plates
47. Insulation device from roll materials
48. Insulation device from polymer and emulsion-bitumen compositions
49. Roofing from roll materials
50. Roofing from piece materials
51. Roofing from polymer and emulsion-bitumen compositions
52. Metal roofing
G. Carpentry
53. Installation of window blocks
54. Installation of door blocks
55. Arrangement of mezzanines, cabinets
H. Flooring
56. Preparation of soil bases for floors
57. Installation of a concrete underlayment, screeds
58. Floor soundproofing device
59. Installation of glued floor waterproofing
60. Device bituminous waterproofing gender
61. The device of monolithic coatings
62. The device of floors from ceramic tiles
63. Arrangement of mosaic floors
64. Installation of floors made of polymeric materials
65. Laying logs in floors on floor slabs
66. Laying logs on posts on a dirt base
67. Arrangement of plank floors
68. The device of floors from block parquet
69. Arrangement of floors from panel parquet
AND. Finishing work
70. Plaster work (simple plaster)
71. Plaster work (improved plaster)
72. Plastering (high quality plaster)
73. Plastering works (coatings from sheets of dry gypsum plaster)
74. Painting works(coloring with water compositions)
75. Painting work (painting with anhydrous compounds)
76. Facing work
77. Wallpaper work
78. Glazing works (glazing of bindings)
79. Glass works (installation of glass blocks and glass panels)
80. Installation of glass profile fences
81. Finishing (facing) of walls with panels, sheets with factory finish
82. Installation suspended ceilings in building interiors
K. Landscaping
83. Drainage device
84. The device blind area of concrete and asphalt concrete
85. The device of sidewalks and paths from plates
86. Device of crushed stone base and asphalt concrete pavement
Part 2. Repair and construction work
1. Repair and strengthening of old foundations
2. Laying of prefabricated reinforced concrete floor slabs during the reconstruction of brick buildings
3. The device of monolithic sections in the ceilings
4. Installation of floor slabs according to metal beams
5. Strengthening brick pillars and piers
6. Installation of metal jumpers
7. Installation of stairs on metal stringers
8. The device of the truss system of wooden elements
9. Repair plaster
10. Repair of plaster facades of buildings
11. Painting of facades
12. Installing facade moldings
13. Installation of downpipes
Part 3. Installation work
1. The device of holes and furrows for laying pipelines
2. Installation of cast iron pressure pipelines
3. Installation of pressure pipelines from asbestos-cement pipes
4. Installation of pipelines for internal cold and hot water supply
5. Installation of reinforced concrete and concrete non-pressure pipelines
6. Installation of sewer pipelines from ceramic pipes
7. System installation internal sewerage and drain
8. Installation of water fittings
9. Bathtub and washbasin installation
10. Installation of sanitary appliances
11. Installation of the internal heating system
12. Installation of metal air ducts
13. Electric lighting device
14. Arrangement of round reinforced concrete wells
15. Installation of chambers of heating mains
16. Installation of impassable channels
17. Insulation of pipelines of heating mains
1.23. Operational quality control should be carried out during construction processes or production operations and ensure the timely detection of defects and the adoption of measures to eliminate and prevent them.
1.24. Operational control performer checks:
Compliance of the sequence and composition of the technological operations performed with the technological and regulatory documentation applicable to these technological operations;
Compliance with technological regimes established by technological maps and regulations;
Compliance of quality indicators of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations
The results of operational control should be documented.
(12-01-2004, clause 6.1.6)
1.25. The executors of operational control are the foremen, foremen and workers of construction laboratories, geodetic and other services of the construction organization, as well as representatives of the customer and the design organization.
The results of the operational quality control are recorded in the journals or in Section 4 of the "General Journal of Work" (Appendix 3)
1.26. During the construction process, an assessment should be made of the performance of work, the results of which affect the safety of the facility, but, in accordance with the accepted technology, become unavailable for control after the start of subsequent work, as well as completed building structures and sections of engineering networks, the elimination of defects of which, identified by control, is impossible without dismantling or damaging subsequent structures and sections of engineering networks. Representatives of the relevant bodies of state supervision, architectural supervision, as well as, if necessary, independent experts may participate in these control procedures. The executor of the works not later than three working days notifies the other participants about the timing of the specified procedures.
The results of the acceptance of work hidden by subsequent work, in accordance with the requirements of the design and regulatory documentation, are documented in certificates of examination of hidden work (Appendix 12). The builder (customer) may require a re-examination after the elimination of the identified defects.
(12-01-2004, paragraphs 6.2, 6.2.1)
Acceptance control
1.27. To the procedure for assessing the conformity of individual structures, tiers of structures (floors), the performer of the work must submit certificates of examination of all hidden works that are part of these structures, geodetic executive schemes, as well as test reports for structures in cases provided for by design documentation and (or) a building contract . The developer (customer) can perform verification of the reliability of executive geodetic schemes presented by the contractor. To this end, the performer of the work must keep the alignment axes and mounting landmarks fixed in kind until the acceptance is completed.
The results of acceptance of individual structures must be documented in acts of acceptance of critical structures (Appendix 13).
1.28. The manual provides forms of certificates of examination of covert work on the acceptance of critical structures.
The list of hidden works and critical structures is determined by the design documentation.
1.29. When erecting complex and unique objects, certificates of examination of hidden works for the acceptance of critical structures should be drawn up taking into account the special instructions and technical conditions of the project documentation.
1.30. In accordance with clause 4.4 of the chapter of SNiP 3.01.03-84, the design organization must also determine the list of critical structures and parts of the structure subject to executive geodetic survey when performing acceptance control.
1.31. Examination of concealed works and intermediate acceptance of critical structures is carried out by commissions with the mandatory participation of representatives:
bridge building department
technical supervision of the customer;
· Design organizations - when accepting critical structures and concealed works provided for by the contract for architectural supervision.
1.32. Inspection and acceptance of works under clause 1.31 is carried out as they are ready. The bridge building division is obliged to call in advance representatives of the technical supervision of the customer and design organizations.
1.33. Certificates of inspection of hidden works and acceptance of critical structures are drawn up in two copies and, after signing, are kept by the contractor and the customer.
1.34. Until the acceptance of hidden work, it is prohibited to carry out subsequent work. It is also prohibited to load completed critical structures of bridges and pipes with construction and operational loads until the acceptance certificate for these structures is issued.
1.35. The following documentation must be submitted during acceptance control:
Executive drawings with introduced (if any) deviations or changes and documents on their agreement with design organizations-developers of drawings;
· factory technical passports, certificates, acts of acceptance by the factory inspection for steel, reinforced concrete and wooden structures;
· certificates or passports certifying the quality of materials used in the production of construction and installation works;
certificates of examination of hidden works;
acts of intermediate acceptance of structures;
Executive geodetic schemes of the position of structures;
work logs;
documents on quality control of welded joints;
acts of testing structures (if tests are provided for by working drawings);
other documents specified in the working drawings.
(3.03.01-87, paragraph 1.22)
Technical Supervision
1.36. The technical supervision of the developer (customer) of the construction is carried out by:
Checking that the contractor has quality documents (certificates in established cases) for the materials, products and equipment used by him, documented results of input control and laboratory tests;
Control over compliance by the performer of works with the rules for warehousing and storage of materials, products and equipment used; if violations of these rules are detected, the technical supervision representative may prohibit the use of improperly stored and stored materials;
· control of compliance of the operational control performed by the contractor with the requirements of SNiP 12-01-2004, clause 6.1.6.
· control of the availability and correctness of the maintenance of as-built documentation by the contractor, including the assessment of the reliability of geodetic executive schemes of the completed structures with selective control of the accuracy of the position of the elements;
control over the elimination of defects in the design documentation identified during the construction process, documented return of defective documentation to the designer, control and documented acceptance of the corrected documentation, its transfer to the contractor;
control over the execution by the contractor of the instructions of the state supervision bodies and local government;
· notification of state supervision authorities about all cases of emergency at the construction site;
· control of compliance of volumes and terms of performance of works with the terms of the contract and the calendar plan of construction;
assessment (together with the work contractor) of the compliance of the work performed, structures, sections of engineering networks, signing of bilateral acts confirming compliance; control over the fulfillment by the contractor of the work of the requirement on the inadmissibility of performing subsequent work until the signing of these acts;
final assessment (together with the work contractor) of the compliance of the completed construction facility with the requirements of legislation, design and regulatory documentation.
To carry out technical supervision, the developer (customer), if necessary, forms a technical supervision service, providing it with design and necessary regulatory documentation, as well as control and measuring devices and tools.
1.37. In cases provided for by law, the developer of project documentation carries out architectural supervision of construction. The procedure for implementation and functions of architectural supervision are established by the relevant regulatory documents.
The remarks of the representatives of the technical supervision of the developer (customer) and architectural supervision are documented. The facts of elimination of defects according to the comments of these representatives are documented with their participation.
(12-01-2004, paragraphs 6.4, 6.5)
1.38. Architectural supervision is carried out on the basis of an agreement (regulatory document) and is carried out, as a rule, during the entire period of construction and commissioning of the facility, and, if necessary, the initial period of its operation.
(SP 11-110-99, paragraphs 4.1,4.2)
1.39. When exercising architectural supervision over the construction of an object, a journal of architectural supervision of construction (hereinafter referred to as the journal) is regularly maintained, which is compiled by the designer and transferred to the customer. Forms for filling out the journal are given in Appendix 5.
(SP 11-110-99, clause 5.1)
1.40. Logging can be carried out both for the construction site as a whole, and for its start-up complexes or individual buildings and structures.
The design of the journal should be carried out in accordance with GOST 2.105-95. The journal must be laced, numbered, decorated with all signatures on the title page and sealed with the customer's seal. The magazine is transferred by the customer to the contractor and is located at the construction site until it is completed. The journal is filled in by the head or specialists exercising architectural supervision, the customer and an authorized person of the contractor.
After construction is completed, the contractor hands over the magazine to the customer.
Each visit to the construction site by specialists is recorded in the journal.
Records and instructions of specialists are set out clearly, with the necessary references to the current building codes and the rules state standards, specifications.
(SP 11-110-99, paragraphs 5.1-5.5)
1.41. Representatives of state control (supervision) bodies, upon notification of the contractor, may participate, in accordance with their authority, in the procedures for assessing the conformity of the results of work hidden by subsequent work and individual structures.
(12-01-2004, item 6.9)
1.42. When discrepancies are identified, the state control (supervision) bodies apply the sanctions provided for by the current legislation.