Installation of equipment for swimming pools. Filtration of water in the pool, which filter to choose

The main difference between the PROPYLENE-POOLS company and its main competitors is the ability to carry out all of the above work on a turnkey basis.

Let's look at each installation stage in more detail.

Installation of a polypropylene pool: installation stages

  1. Preparing a pit for a polypropylene pool.
  2. Pouring a reinforced concrete slab under the base of a polypropylene pool.
  3. Installation of a propylene pool bowl in a pit and placing it on the horizon.
  4. Installation of the necessary pool equipment and connection to the sewerage system.
  5. Filling the pit with concrete mixture.
  6. Decorative finishing of the area around the pool.

Correct installation of a polypropylene pool is the key to its long and, most importantly, safe operation. requires a professional approach.

  1. Preparing a pit for a polypropylene pool

    The length and width of the pit should exceed the dimensions of the propylene pool bowl by 0.75-1 m around the perimeter. The depth of the pit consists of the following main layers:

    – sand and gravel cushion – 150-200 mm
    - reinforced concrete slab under the base of the bowl - 200-250 mm
    - lining material (geotextile, insulation, film) - 25mm
    - the height of the vertical wall of the pool.

    It should be taken into account that the upper edge of the pool can rise above the ground surface to a height of no more than 300 mm. If possible, you should avoid installing a pool in areas with high groundwater levels. If there is groundwater at the site where the pool is installed, our company can provide both advisory services on water control and carry out surface drainage measures.

  2. Pouring a reinforced concrete slab under the base of the pool

    Before making a concrete slab, the bottom of the pit should be leveled with a sand and gravel cushion. The recommended thickness of the concrete slab is 200-250 mm with one or two reinforcing mesh (reinforcement thickness 10-12 mm in increments of 200-250 mm). The dimensions of the slab must exceed the overall dimensions of the bottom of the pool bowl by at least 250 mm around the perimeter. The surface of the slab must be leveled and have a smooth appearance (maximum deviation from the horizontal +3 mm).

  3. The manufacture of a polypropylene pool is possible from polypropylene sheets on site, or the installation of a previously welded pool bowl is carried out by a team of several people in compliance with safety regulations. After installation, the bowl should be placed in the horizon.

  4. Installation of a propylene pool bowl in a pit and placing it on the horizon
  5. The propylene pool is equipped with the necessary set of equipment for filtration, heating and water preparation. Pool equipment is connected to each other by pipelines through fastening fittings. All pipes are led to the technological room where the filter unit is installed.

    Manufacturing a polypropylene pool is a particularly important task, since it is necessary to ensure complete waterproofing between the pool wall and the embedded part. This work should only be performed by professional, trained crews.

  6. Filling the pit with concrete mixture

    The pool is filled with concrete mixture in stages. Each layer has a height of no more than 40–50 cm. The propylene pool is filled with water to a level of 40–50 cm. Next, the pit is filled with concrete mixture to the water level. After the concrete has cured, the operation is repeated until the entire pit is completely filled.

    Considering that this operation is not of a particularly responsible nature, it can be performed by the client himself. However, at the request of the customer, our company can provide this service.

  7. Decorative finishing of the area around the pool

    The final stage of pool installation. The area around the propylene pool can be finished at the customer's request in any possible way. If necessary, this work can also be performed by our team.

Thus, making polypropylene pools is not as complicated a process as it seems.

AstraPool's many years of experience in installing and servicing a wide variety of swimming pool modifications allows us to install equipment efficiently and reliably.

The experience and qualifications of our company’s employees guarantee the fulfillment of all undertaken obligations for the installation of equipment for swimming pools, regardless of the complexity of the work performed.

Equipment installation usually includes:

  • installation of a water supply system,
  • various filters,
  • equipment for disinfection and heating,
  • systems for hydromassage and artificial flow creation.

The rules for installing equipment during the construction of public and sports swimming pools are regulated by sanitary and epidemiological standards. They generally do not apply to private swimming pools, but for safety reasons these rules and regulations should still be followed.

Benefits of working with AstraPool

  • When ordering installation, there is a 10% discount on swimming pool equipment.
  • Equipment installation is carried out using a wide range of the most modern high-tech devices.
  • Affordable competitive prices for equipment.
  • The shortest time possible for installation of equipment for swimming pools without compromising their quality.
  • High professionalism and continuous training of employees.
  • Fast delivery and installation of equipment for swimming pools in Moscow to other regions of Russia.

Our clients can use not only the services of experienced specialists in the installation of water heating and filtering equipment for swimming pools, but also the installation of skimmers and other additional equipment.

Our installation services can include a variety of ambiance and relaxation devices that will make your pool a great place to relax for you and your guests.

Installation of water supply and drainage equipment

If the pool is located within the city limits or where there is a centralized water supply and sewerage system, then, as a rule, there are no problems with water supply and drainage. But in swimming pools located in country houses, water supply and drainage are carried out using pumps of varying power.

Installation of this equipment must be carried out in accordance with certain rules, otherwise using the pool will not be comfortable enough.

Filtration system installation

Proper installation of filter equipment during the construction of swimming pools is of great importance.

Filters must be selected taking into account the volume of water and the speed of its circulation.

Modern pool filters are capable of performing biological and mechanical water purification using filter cartridges or sand backfill.

Installation of disinfection equipment

Such devices are used to dose the pool with special chemicals for swimming pools, capable of suppressing the vital activity of various microorganisms.

Today, ozone, chlorine and activated oxygen are most often used for these purposes. These reagents are mixed with coagulants, which bind organic matter and raise it to the surface of the water.

Installation of water heaters

Water heaters are tubular heating elements with an automatic control system. These pool systems monitor the water temperature and adjust it to a predetermined level.

Correct and high-quality installation of water heaters will make your pool as comfortable to use as possible, and fresh, warm and clean water will perfectly relieve the stress accumulated during a hard day at work.

Installation of additional equipment

Today it is very popular to equip swimming pools with additional equipment - stairs and slides, geysers and hydromassages.

They can be made according to an individual design to give the pool a unique look.

We also install equipment for artificial lighting and additional pool lighting.

At the client’s request, AstraPool specialists will select and install equipment in the pool to create the effect of an artificial flow or waterfall.

The cost of installation includes the price of equipment for the pool, its delivery to the work site, performance testing and adjustment, and familiarization of future users with operating rules.

Installation of a polypropylene pool includes:

  • pit preparation;
  • installing a cushion and pouring a slab under the base;
  • installing the bowl and leveling it;
  • installation of equipment;
  • pouring the pit with concrete;
  • installation of a decorative area around the perimeter of the pool.

When performing this complex of work, craftsmen should pay attention to the following:

  • the upper edge of the pool should not be more than 0.3 m above ground level;
  • the width and length of the pit should be 0.8 - 1 m larger than the dimensions of the bowl around the perimeter;
  • before pouring the concrete slab, the bottom of the pit is leveled with a sand and gravel cushion;
  • the slab must be at least 0.25 m larger than the bowl around the perimeter;
  • Filling the pit with concrete should be done in stages, with the bowl filled with water to the same level and only then concrete is poured flush with it.

Ready-made pools

A polypropylene pool can be assembled according to an individual project, or you can buy a ready-made pool in one of the standard shapes. A factory-made bowl has an aesthetic advantage - the seams are not visible. No matter how much manufacturers say that when assembled on site, the seams are not visible, this is not always true. Despite all the mechanical strength of such a joint, it often remains visually noticeable. Thus, the finished bowl will have a more attractive appearance.

The range of ready-made polypropylene pools often includes round and rectangular bowls. However, depending on the manufacturer, exceptions to this rule are possible. The standard thickness of the bowl walls is 8 mm, although the permissible thickness can be 5-10 mm.

Approximate prices for ready-made bowls of polypropylene pools with a depth of 1.5 m

Form Dimensions, m Volume price, rub.
Round Diameter: 2.5 7.36 m 3 34500,00
Round Diameter: 2.9 9.91 m 3 40600,00
Rectangular 3.0x2.0 9 m 3 40600,00
Rectangular 4.0x5.0 15 m 3 55600,00
Rectangular 4.0x2.9 17.4 m 3 63000,00
Rectangular 5.0x2.5 18.75 m 3 66300,00
Rectangular 5.0x2.9 21.75 m 3 72700,00
Rectangular 6.0x2.5 22.5 m3 72700,00
Rectangular 6.0x2.9 26.1 m3 84400,00
Rectangular 6.5x2.9 28.28 m3 92500,00

$ Pool installation. Cost in Moscow

The final price for pool installation work depends on its shape and size, the complexity of the pit and the connected equipment.

Estimated cost of installing equipment for a round pool with a diameter of 2.9 m and a depth of 1.5 m.

Name of equipment or work Price, rub
Filtration unit 20020,96
Control unit for filtration and lighting systems 10385,87
Transformer 1564,14
LED RGB underwater light (multi-color) 7758,12
Check valve 1063,61
Faucet 2 pcs. 2127,23
Fittings, adapters 2815,45
Pipe 2815,45
Skimmer+nozzle 2565,19
Ladder 10886,40
Filtrate 875,92
Channel with electrical wiring 5 m. 1251,31
Total 64129,64
Departure of the brigade 5000,00
Equipment assembly 16032,41
Total 85162,05

In more detail, the cost of installing a specific pool will be calculated for you by craftsmen, whom you can find in the ThisDom catalog.
Hide

An artificial pond is a necessary thing for those who live outside the city or visit the countryside from time to time.

Many country house owners dream of building their own swimming pool. And this is a completely feasible idea. You can buy a pool, order it from a special company, or build it yourself, saving a lot of money.


Depending on the complexity of the design and assembly conditions, there are several types of pools: frame, stationary and inflatable. How difficult it will be to install pools depends on this.

Frame pools

Such a frame is covered with PVC fabric. A wide selection of sizes and colors will help you customize your pool to suit your mood.

Pools consisting of a “skeleton”, depending on the complexity of the design, come in several types: they can be used only in the warm season, they can be used all year round and of a solid design, which requires a more complex design. A frame pool consists of a special edge, which gives stability and strength to the structure, and of course a water tank.

In order to install a specific pool, which consists of a frame, you must have the following tools on hand: a set of keys - simple, with six edges and an adjustable one, screwdrivers, and also a cutting tool. Also, in order to level the site, you will need additional materials - a wooden peg, high-density polyethylene film, polystyrene or foam boards and adhesive tape.

Return to contents

Installation, step-by-step execution

Before installing such a pool, you need to choose the right place to mount it. The location for the pool should be level, it is even advisable that the pool itself be located on a slight hill for good water drainage. There should be no trees or buildings near the pool. In order to create a good place for its installation, you need to level the site, remove all debris - small branches, grass, to prevent them from rotting under the bottom of the device, and pour sifted sand over the entire site in an even layer of 1-1.5 cm.

Also, close to the pool, you need to have access to electricity to connect some of its units, to water, in order to fill it and to drain used water.

Now you can install the pool:

A frame pool is quite easy to install and just as easy to dismantle for the winter.

  1. In the middle of the site you need to install a small stake made of wood, put the first layer of pool film on it and pierce it with a stake so that the film does not move and remains in place.
  2. We lay foam plastic or polystyrene foam boards on top of the film, moving them down a little. After all the slabs are laid, they need to be secured together with adhesive tape, and the excess ends of the slabs should be cut off with a knife. The thickness of polystyrene foam boards must be at least 2 cm.
  3. Then you need to trim the top of the stake so that it is flush with the slabs.
  4. On the prepared area we place a special mat that comes with the pool and position it so that the drain hole is in the right place.
  5. Remove the drainage valve from the hose and leave it for a couple of minutes so that the pool material can heat up evenly in the sun.
  6. The beams that will be positioned horizontally have a larger caliber and must be inserted into certain grooves at the bottom of the structure.
  7. Then, using bolts, you need to screw the hinges to the ends of the beams along the entire perimeter of the structure.
  8. The next step is to install the supports into the loops of the rope. To do this, first insert the lower part of the support into the rope grommet, then the upper part into the hinge, insert the support into the groove of the hinge, align the pins on the springs and connect the support cap to the support itself.
  9. After the pool structure is assembled, you need to check its strength. To do this, take the assembled structure by the upper part and shake it thoroughly.
  10. We insert the pool bowl inside the structure and glue it to the walls of the frame with adhesive tape. In this case, it is advisable not to immediately fix the bowl over the entire frame, but to include a set of water in it and carefully straighten the fabric while it is collected. This will help distribute the bowl fabric evenly within the pool frame.

After the pool is completely assembled, you need to check how level it is, since its correct location determines whether there will be a water leak or not. In order to check how the pool stands, you need to fill it with water about 3 cm and carefully look to see if there is any difference in the water levels around its entire perimeter.

Return to contents

Inflatable pools

The most comfortable and least labor-intensive to install are inflatable pools, which are made from a special durable film. In order to install an inflatable pool, you need to place it on a flat surface, on which there will be no things that could tear it - grass, shells, pebbles. It’s good to unroll the fabric and pump it up with the pump that comes with the pool.